Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Work Problem: Re-opening a thread

Expert replies
by kanha81 » Thu Apr 23, 2009 12:32 pm
Is there an efficient way to solve these type of problems?

Working alone, Maria can complete a task in 100 minutes. Shaniqua can complete the same task in two hours. They work together for 30 minutes when Liu, the new employee, joins and begins helping. They finish the task 20 minutes later. How long (in minutes) would it take Liu to complete the task alone?

A. 180
B. 240
C. 200
D. 160
E. 220

OA [spoiler][/spoiler]
Want to Beat GMAT.
Always do what you're afraid to do. Whoooop GMAT
Join the discussion
Source: — Problem Solving |

Re: Work Problem: Re-opening a thread

by Vemuri » Thu Apr 23, 2009 7:37 pm
Given, M can do the work in 100mins & S can do the same work in 120mins.

Remember the standard rate formula ==> rate = work/time

M can do the work alone in 100mins. This means that she can do 1/100th of the work in 1 minute. Similarly, S can do 1/120th of the work in 1 minute. So, in 1 minute both M & S can do (1/100 + 1/120)th of the work. The expression reduces to 11/600.

If M & S work for 30 minutes together, then 30*11/600 ==> 11/20th of the work is completed. Hence, the remaining work is 1-(11/20) ==> 9/20.

The question stem says that Liu joins at this stage & the remaining work is completed in 20mins. So, 20 * (1/100 + 1/120 + 1/L) = 9/20
==> 1/5 + 1/6 + 20/L = 9/20
==> 20/L = 9/20-1/5-1/6
==> 20/L = 1/12
==> L = 240. So, L alone can do the work in 240mins.

Hope this helps.
Join the discussion

by vittalgmat » Fri Apr 24, 2009 12:45 am
Awesome explanation Vemuri !!!!!.
Join the discussion

Re: Work Problem: Re-opening a thread

by kanha81 » Fri Apr 24, 2009 8:11 am
Vemuri wrote:Given, M can do the work in 100mins & S can do the same work in 120mins.

Remember the standard rate formula ==> rate = work/time

M can do the work alone in 100mins. This means that she can do 1/100th of the work in 1 minute. Similarly, S can do 1/120th of the work in 1 minute. So, in 1 minute both M & S can do (1/100 + 1/120)th of the work. The expression reduces to 11/600.

If M & S work for 30 minutes together, then 30*11/600 ==> 11/20th of the work is completed. Hence, the remaining work is 1-(11/20) ==> 9/20.

The question stem says that Liu joins at this stage & the remaining work is completed in 20mins. So, 20 * (1/100 + 1/120 + 1/L) = 9/20
==> 1/5 + 1/6 + 20/L = 9/20
==> 20/L = 9/20-1/5-1/6
==> 20/L = 1/12
==> L = 240. So, L alone can do the work in 240mins.

Hope this helps.
Excellent explanation, mate! Thanks a bunch. It really makes it easier to understand.
Want to Beat GMAT.
Always do what you're afraid to do. Whoooop GMAT