BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Work and rate

Expert replies
by GMATMadeEasy » Fri Oct 08, 2010 2:38 pm
A and B can do a work together in 18 days, B and C in 24, and A and C in 36. They all work together for 4 days and then A left. In how many more days can B and C finish the remaining work?
(A) 6
(B) 8
(C) 12
(D)16
(E) 18


What is the fastest way to solve this problem ?
Join the discussion
Source: — Problem Solving |

by sanabk » Fri Oct 08, 2010 3:55 pm
E

A, B work together in 18 days => A+B=18 days => A+B = (1/18)th work in 1 day
B, C work together in 24 days => B+C=24 days => B+C = (1/24)th work in 1 day
C, A work together in 36 days => C+A=36 days => C+A = (1/36)th work in 1 day
--------------------
2(A+B+C) = (9/72)th work in 1 day
(A+B+C) = (9/144)th work in 1 day
(A+B+C) = 4*(9/144)th work in 4 days = (1/4)th work in 4 days

After A+B+C working for 4 days the part of work remaining is 1-(1/4)=(3/4)th work

B+C = (1/24)th work in 1 day
(3/4)th work will take = (3/4)/(1/24)=18 days
Join the discussion

by diebeatsthegmat » Fri Oct 08, 2010 6:54 pm
sanabk wrote:E

A, B work together in 18 days => A+B=18 days => A+B = (1/18)th work in 1 day
B, C work together in 24 days => B+C=24 days => B+C = (1/24)th work in 1 day
C, A work together in 36 days => C+A=36 days => C+A = (1/36)th work in 1 day
--------------------
2(A+B+C) = (9/72)th work in 1 day
(A+B+C) = (9/144)th work in 1 day
(A+B+C) = 4*(9/144)th work in 4 days = (1/4)th work in 4 days

After A+B+C working for 4 days the part of work remaining is 1-(1/4)=(3/4)th work

B+C = (1/24)th work in 1 day
(3/4)th work will take = (3/4)/(1/24)=18 days
wow.... this is so complicating....
1/a+1/b=1/18
1/b+1/c=1/24
1/c+1/a=1/36
add them above all together <=> 2(1/a+1/b+1/c)=9/72 thus together they finish the work in 16 days
so in h4 days they only finish 1/4 job and 3/4 job leff is for B+C
b+c finish 1 work in 24 days thus they will do 24*3/4=18 days to finish the left job.
Join the discussion

by neerajkumar1_1 » Fri Oct 08, 2010 7:05 pm
diebeatsthegmat wrote:
sanabk wrote:E

A, B work together in 18 days => A+B=18 days => A+B = (1/18)th work in 1 day
B, C work together in 24 days => B+C=24 days => B+C = (1/24)th work in 1 day
C, A work together in 36 days => C+A=36 days => C+A = (1/36)th work in 1 day
--------------------
2(A+B+C) = (9/72)th work in 1 day
(A+B+C) = (9/144)th work in 1 day
(A+B+C) = 4*(9/144)th work in 4 days = (1/4)th work in 4 days

After A+B+C working for 4 days the part of work remaining is 1-(1/4)=(3/4)th work

B+C = (1/24)th work in 1 day
(3/4)th work will take = (3/4)/(1/24)=18 days
wow.... this is so complicating....
1/a+1/b=1/18
1/b+1/c=1/24
1/c+1/a=1/36
add them above all together <=> 2(1/a+1/b+1/c)=9/72 thus together they finish the work in 16 days
so in h4 days they only finish 1/4 job and 3/4 job leff is for B+C
b+c finish 1 work in 24 days thus they will do 24*3/4=18 days to finish the left job.
its not complicated as such...
ofcourse when u attack such a question for the first time, it seems complicated.. ..

but remember the way this problem is solved and the logic been used behind it..

the question could also ask you that how much time would each of them take individually to complete the work... in which case after u get the combined rate... all u need to do is:
say work time for A = total - (time of B and C)

total u already found out..
time of B and C is given to you...

u can follow the same method for the rest of them..

Hope this further Helps! .. :)
Join the discussion

by Yanat » Fri Oct 08, 2010 9:56 pm
A and B can do a work together in 18 days, B and C in 24, and A and C in 36. They all work together for 4 days and then A left. In how many more days can B and C finish the remaining work?
(A) 6
(B) 8
(C) 12
(D)16
(E) 18

A+B in one day = 1/18 of work
B+C in one day = 1/24 of work
A+C in one day = 1/36 of work

So In 4 days A+B+C = 1/4 of work. Now A leaves. So we have B+C left. Now pending work is 1-1/4= 3/4

If B+C in one day = 1/24 of work, so B+C can complete 3/4 of the work in 18 days.

IMO it is E.

Can someone post the correct answer
Join the discussion

by GMATGuruNY » Sat Oct 09, 2010 4:16 am
GMATMadeEasy wrote:A and B can do a work together in 18 days, B and C in 24, and A and C in 36. They all work together for 4 days and then A left. In how many more days can B and C finish the remaining work?
(A) 6
(B) 8
(C) 12
(D)16
(E) 18


What is the fastest way to solve this problem ?
When the job is undefined, plug in!

Plug in job = 72.
Rate for A+B = w/t = 72/18 = 4.
Rate for B+C = w/t = 72/24 = 3.
Rate for A+C = w/t = 72/36 = 2.
Combining the rates, we get:
(A+B) + (B+C) + (A+C) = 4+3+2
2A + 2B + 2C = 9
A+B+C = 9/2
Work completed in 4 days = r*t = 9/2 * 4 = 18.
Remaining work = 72-18 = 54.
Time for B+C to finish = w/r = 54/3 = 18.

The correct answer is E.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion