\(M\) and \(N\) working together, can finish a job in 6 days. With the help of \(P,\) they completed the job in 4 days.

Expert replies
by M7MBA » Sun Jun 21, 2020 2:24 pm

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty

\(M\) and \(N\) working together, can finish a job in 6 days. With the help of \(P,\) they completed the job in 4 days. If \(Q\) joined them, all 4 together would have completed the job in \(3\frac13\) days. If all work at their respective constant rate, then in how many days \(Q\) alone can complete the work?

A. 10
B. 12
C. 15
D. 18
E. 20

[spoiler]OA=E[/spoiler]

Source: e-GMAT
Join the discussion
Source: — Problem Solving |

M7MBA wrote:
Sun Jun 21, 2020 2:24 pm
\(M\) and \(N\) working together, can finish a job in 6 days. With the help of \(P,\) they completed the job in 4 days. If \(Q\) joined them, all 4 together would have completed the job in \(3\frac13\) days. If all work at their respective constant rate, then in how many days \(Q\) alone can complete the work?

A. 10
B. 12
C. 15
D. 18
E. 20

[spoiler]OA=E[/spoiler]

Source: e-GMAT
Given that \(M\) and \(N\) working together, can finish a job in 6 days, let's club M and N and rename them R.

So, we have

R can finish a job in 6 days;
R & P working together can finish a job in 4 days;

Let's club R and P and rename them S.

So, we have

=> S can finish a job in 4 days
S & Q working together can finish a job in \(3\frac13\) days

With these data, we deduce

No. of days required for Q to finish the job = Reciprocal of \(\frac1{3\frac13}) – \frac14 = \frac 3{10} - \frac14=\frac{6-5}{20}=\frac1{20}\)

= 20 days

Correct answer: E

Hope this helps!

-Jay
_________________
Manhattan Review GMAT Prep

Locations: Manhattan SAT | GMAT Practice Questions | GRE Practice Test | LSAT Info | and many more...

Schedule your free consultation with an experienced GMAT Prep Advisor! Click here.
Join the discussion