BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Difficult Work/Rate Problem

Expert replies
by mattocks » Sun Mar 28, 2010 11:23 am
Can someone explain the best way to solve this problem?

13 men and 7 boys can finish a job in 7 days, while 6 boys and 13 women can finish the same job in 6 days. In how many days can 1 man, 1 boy and 1 woman working together finish the same job (assume constant rates each for men, women, and boys)?

a) 42
b) 54
c) 21
d) 63
e) 24
Join the discussion
Source: — Problem Solving |

by thephoenix » Sun Mar 28, 2010 8:47 pm
mattocks wrote:Can someone explain the best way to solve this problem?

13 men and 7 boys can finish a job in 7 days, while 6 boys and 13 women can finish the same job in 6 days. In how many days can 1 man, 1 boy and 1 woman working together finish the same job (assume constant rates each for men, women, and boys)?

a) 42
b) 54
c) 21
d) 63
e) 24
IMO A
Attachments
work time11.xls
(13.5 KiB) Downloaded 112 times
Join the discussion

by harshavardhanc » Mon Mar 29, 2010 2:50 am
mattocks wrote:Can someone explain the best way to solve this problem?

13 men and 7 boys can finish a job in 7 days, while 6 boys and 13 women can finish the same job in 6 days. In how many days can 1 man, 1 boy and 1 woman working together finish the same job (assume constant rates each for men, women, and boys)?

a) 42
b) 54
c) 21
d) 63
e) 24
13M + 7B = 1/7 (per day work of 13 men and 7 boys)
13W + 6B = 1/6 (per day work of 13 women and 6 boys)
------------------------------
13M+13W+13B = 13/42

per day work of (M+W+B) = 1/42. Hence, number of days required for 1 man, 1 woman, and 1 boy = 42 days.
Regards,
Harsha
Join the discussion

by pops » Mon Mar 29, 2010 6:42 am
mattocks wrote:Can someone explain the best way to solve this problem?

13 men and 7 boys can finish a job in 7 days, while 6 boys and 13 women can finish the same job in 6 days. In how many days can 1 man, 1 boy and 1 woman working together finish the same job (assume constant rates each for men, women, and boys)?

a) 42
b) 54
c) 21
d) 63
e) 24
Hi,
Trick here would be to notice the pattern of numbers : 13, 7, 6 ....
now make an equation as per given condition:
13 * 1/m + 7 * 1/b = 1/7
13 * 1/w + 6 * 1/b = 1/6

[quickly realise that 7/b + 6/b =13/b and we are asked to know 1/m+1/w+1/b]
so, add above 2:
13 * (1/m+1/w+1/b) = 1/7 + 1/6 = 13/42
hence, the answer = 42 :-)
Join the discussion

by eaakbari » Mon Mar 29, 2010 1:47 pm
Using information given form the equations

13/x + 7/y = 1/7
6/y +13/z = 1/6

Here we have 3 variables and 2 equations which is unsolvable, that means theres some trick, so observing the equations, we realize their sum gives us the answer

Answer A
Join the discussion

by akhpad » Tue Mar 30, 2010 1:35 am
7(13M+7B) = 6(6B+13W) = k(M+B+W)


(13M+7B) = k(M+B+W)/7
(6B+13W) = k(M+B+W)/6
sum these two

13M+13B+13W = k(M+B+W)(1/7 + 1/6)

k = 42
Join the discussion

by kstv » Tue Mar 30, 2010 8:31 am
pops wrote: Trick here would be to notice the pattern of numbers : 13, 7, 6 ....
now make an equation as per given condition:
13 * 1/m + 7 * 1/b = 1/7
13 * 1/w + 6 * 1/b = 1/6
[quickly realise that 7/b + 6/b =13/b and we are asked to know 1/m+1/w+1/b]
so, add above 2:
13 * (1/m+1/w+1/b) = 1/7 + 1/6 = 13/42
hence, the answer = 42 :-)
13 M + 7 B = 7 days ---1 and 6 B + 13 W = 6 days ----2
LCM of 7 and 6 = 42
13M+7B in 42 days can do 6 times the work ---1
......6B + 13 W in 42 days can do 7 times the work-------2 Adding 1 and 2
13M+13B+13W in 42 days can do 13 times the work so dividing by 13
M+B+W can in 42 days can do the the work once.