BTGmoderatorDC wrote:Ten theater students are to begin work on a set for a musical. Working at a constant rate, they will finish the set in 60 days, but the director of the musical decides they need to finish in 50 days. How many more theater students, working at the same constant rate, must work to finish the set on time?
A. 2
B. 3
C. 5
D. 10
E. 12
(50 days)/(60 days) = 5/6.
To finish the job in 5/6 of the normal time, the crew requires 6/5 of the normal number of students -- an increase of 1/5:
(1/5)(10) = 2 more students.
The correct answer is
A.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.
As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.
For more information, please email me (Mitch Hunt) at
[email protected].
Student Review #1
Student Review #2
Student Review #3