GMAT PREP

This topic has expert replies
Source: — Data Sufficiency |

Junior | Next Rank: 30 Posts
Posts: 10
Joined: Wed Nov 05, 2008 12:24 am

by wally » Wed Apr 15, 2009 8:16 pm
Breaking it down in parts to build a suitable equation that describes what is happening:

A Contractor combine x tons of a gravel mixture that contained 10 percent gravel G, by weight,

X tons x 0.1G = X0.1G

with y tons of a micture that contained 2 percent gravel G, by weight,

Y tons x 0.02G = Y0.02G

to produce z tons ofa mixture that was 5 percent gravel G, by weight. What is the value of x?

Z tons x 0.05G = Z0.05G

The complete expression is therefore:

X0.1G + Y0.02G = Z0.05G

We can divide both sides of the equation to disregard G, thus the expression becomes:

X0.1 + 0.02Y = Z0.05 --- (A)

Implied in the question is a constraint that X + Y = Z. Using a logical example, if we add 2 tons of gravel (X) to 3 tons of gravel (Y) we must end up with 5 tons of gravel (Z).

X + Y =Z ---(B)

Using equation (A) and (B) to describe the what is happening we can now evaluate the sufficiency of statement 1.

1) Y= 10

Therefore:

Equation B becomes
X + 10 = Z

Substituting this into equation A we get
0.1X + 0.02(10) = 0.05(X + 10)

We can continue to solve but at this stage one should be able to see that we have a sufficient solution for X. SUFFICIENT

1) z = 16

Equation B becomes
X + Y = 16
Y = 16 - X

Substituting into Equation A we get
0.1X +0.02Y = 0.05(16)
Furthermore Y = 16 - x
0.1X + 0.02(16 - X) = 0.05(16)

Again, we can continue to solve but with one linear equation and one variable it is clear we can arrive at a value for X. SUFFICIENT

Therefore, ANSWER is D. Each statement alone is sufficient.

User avatar
Master | Next Rank: 500 Posts
Posts: 246
Joined: Mon May 19, 2008 7:34 am
Location: Texaco Gas Station
Thanked: 7 times

by cubicle_bound_misfit » Wed Apr 15, 2009 8:57 pm
basically you get two equations

x+y=z

and

.05z=.1x+.02y

each stmt reduces one variable and hence x is solvable. Hence D.
Cubicle Bound Misfit