BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Work problem

Expert replies
by nadib002 » Mon May 09, 2011 2:27 pm
A, B and C can finish a piece of work in 30, 40, and 60 days respectively. 10 days after they started to work together B leaves. 4 days after B left, A leaves and C completes the remaining work. Find how many days C had worked altogether.

This is how i did it: Please let me know if there is another easier way of solving it:

rate of A = 1/30

rate of B = 1/40

rate of C = 1/60

Work completed by all 3 in 10 days is W = rate * time


(1/30 + 1/40 + 1/60) * 10 = 3/4


Work left to complete = 1-3/4 = 1/4


Since B left after 10 days, the remaining work will have to be finished by A + C

rate of A + C together = (1/30 + 1/60)

Work done by A+C = (1/30 + 1/60) * 4 = 1/5

Work Left for C to complete alone = 1/4 - 1/5 = 1/20

Time required for C to complete 1/20 work alone = rate of C * time = 1/60 * time

Therefore time required for C to complete the remaining , 1/20 of the work @ 1/60 = 3 days

Total days worked by C = 10 + 4 + 3 = 17 days
Last edited by nadib002 on Mon May 09, 2011 2:53 pm, edited 1 time in total.
Join the discussion
Source: — Problem Solving |

by djiddish98 » Mon May 09, 2011 2:46 pm
1/30 + 1/40 + 1/60 = Completion in 1 day when working all 3 together = 8/240 + 6/240 + 4/240 = 18/240 = 9/120 = 3/40.

They all work together for 10 days - 3/40 * 10 = 30/40 = 3/4 done before B leaves.

B leaves - now working at 1/30(2/60) + 1/60 = 3/60 = 1/20 per day.

Do that for 4 days so 4*(1/20) = 1/5 completed before A leaves.

3/4 + 1/5 = 19/20 completed. All that's left is C now, working 1/60 per day. Needs to complete 1/20 or 3/60 units, so add 3 more days.

I'm getting a total of 10 days + 4 days + 3 days = 17 days.
Join the discussion

by GMATGuruNY » Mon May 09, 2011 2:53 pm
nadib002 wrote:A, B and C can finish a piece of work in 30, 40, and 60 days respectively. 10 days after they started to work together B leaves. 4 days after B left, A leaves and C completes the remaining work. Find how many days C had worked altogether.
Let job = 120 units.

Rate for A = w/t = 120/30 = 4 units per day.
Rate for B = w/t = 120/40 = 3 units per day.
Rate for C = w/t = 120/60 = 2 units per day.

Combined rate for A+B+C = 4+3+2 = 9 units per day.
Over 10 days, work completed by A+B+C = r*t = 9*10 = 90 units.

Combined rate for A+C = 4+2 = 6 units per day.
Over 4 days, work completed by A+C = 6*4 = 24 units.

Remaining work = 120-90-24 = 6 units.
Time for C to finish = w/r = 6/2 = 3 days.

Total days for C = 10+4+3 = 17 days.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by nadib002 » Mon May 09, 2011 3:08 pm
Thank you all for replying

The answer is 17 days.

@Mitch

I saw that you plugged in numbers. I did it using algebra. When should one plug in numbers vs algebra?

Thank you
Join the discussion

by GMATGuruNY » Mon May 09, 2011 3:21 pm
nadib002 wrote:Thank you all for replying

The answer is 17 days.

@Mitch

I saw that you plugged in numbers. I did it using algebra. When should one plug in numbers vs algebra?

Thank you
The approaches are the same: each determines respective rates for A, B and C.
The key difference: by plugging in a value for the job, we can solve using only integer values. No messy fractions.
For most rate problems, I plug in a value for the job.
Use whichever approach you prefer.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion