BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

pumps

Expert replies
by shibal » Sun Jul 12, 2009 1:31 pm
two water pumpss working together can fill a pool in 4 hrs. if the constant rate of one pump is 1.5 times the other, how many hours would take fot the faster pump to fill the pool alone?

oa [spoiler]20/3[/spoiler]
Join the discussion
Source: — Problem Solving |

by VP_Jim » Sun Jul 12, 2009 1:42 pm
Let's say that that pool has a capacity of 100 gallons. Now, we know that it takes both pumps working together 4 hours to fill the pool, so their combined rate is 25 gallons per hour.

We know that one pump's rate is 1.5x the other one's rate, so we can set up an equation:

Pump A's rate + Pump B's rate = Total rate
1.5x + x = 25
2.5 x = 25
x = 10

So, the slower pump's rate is 10 and the faster pump's rate is 15 (10 x 1.5).

Now, remember that we said the pool was 100 gallons. The faster pump will take 100/15 = 20/3 hours to fill it.

Plugging in values is a great way to do work and rate problems such as this, when the "job" - in this case, how big the pool is - is unknown.
Jim S. | GMAT Instructor | Veritas Prep
Join the discussion

by shibal » Mon Jul 13, 2009 3:43 pm
is there a way of doing this w/out plugging in numbers?
Join the discussion

by ssmiles08 » Mon Jul 13, 2009 4:28 pm
shibal wrote:is there a way of doing this w/out plugging in numbers?
1/(3x/2) + 1/x = 1/4

(2+3)/3x = 5/(3x)



5/(3x) = 1/4

x = 20/3

the rate for the first one is 1/10 (1.5*20/3)
the rate for the second one is 1/(20/3) ( 1*20/3)

So the first machine pumps 1 tank in 10 hours
the second pumps 1 tank is 6.667 hours.

clearly the second tank has the faster rate, it pumps in 20/3 hours.
Join the discussion