gmatnmein2010 wrote:A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61-st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?
(A) 4
(B) 5
(C) 6
(D) 7
(E) 8
Let an imaginary unit be 110 works.
1 man will complete the 110works in 1100 days.Hence, in 1 day only 0.1work
Till day 60 work done = 60works.
Now,50 works left.
6 more ppl hired.Hence,16 man crew so works done in 1 day = 16x0.1 = 1.6works
Hence,days required = 50/1.6=31.25 which is 32.
so,92 days .
hence [spoiler]8(100-92) E.[/spoiler]