Randy can rebuild an automobile engine in a hours. Alvin can rebuild the same engine in b hours. If Randy and Alvin work together at their respective rates to rebuild the engine, which of the following represents the portion of the job that Randy will not have to complete?

A. ab/(a+b)
B. (a-b)/(a+b)
C. b/(b-a)
D. a/(a+b)
E. b/(a+b)
Regards,
Sunit

________________________________

Kill all my demons..And my angels might die too!

User avatar
Community Manager
Posts: 1060
Joined: Fri May 13, 2011 6:46 am
Location: Utrecht, The Netherlands
Thanked: 318 times
Followed by:52 members

by neelgandham » Sun Aug 19, 2012 11:03 am
If Randy can rebuild an automobile engine in a hours. What part of the automobile can he rebuild in 1 hour ? It is 1/a

Similarly, If Alvin can rebuild the same engine in b hours. What part of the automobile can he rebuild in 1 hour ? It is 1/b.

In one hour Randy and Alvin working together can rebuild (1/a + 1/b)th part of an automobile.
Total time taken by Randy and Alvin to rebuild the automobile = 1/(1/a + 1/b) = ab/(a+b) hours

Portion of work Randy completed in ab/(a+b) hours = [ab/(a+b)]*1/a = b/(a+b)
Portion of work Randy will not have to complete = 1 - [b/(a+b)] = a/(a+b)

IMO D

A. ab/(a+b)
B. (a-b)/(a+b)
C. b/(b-a)
D. a/(a+b)
E. b/(a+b)
Anil Gandham
Welcome to BEATtheGMAT | Photography | Getting Started | BTG Community rules | MBA Watch
Check out GMAT Prep Now's online course at https://www.gmatprepnow.com/

User avatar
Senior | Next Rank: 100 Posts
Posts: 94
Joined: Sat Mar 31, 2012 3:39 am
Location: Calcutta
Thanked: 8 times

by cypherskull » Sun Aug 19, 2012 11:12 am
Thanks Anil! That helped.