BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

PS Help..

Expert replies
by ramonsa » Wed Jun 03, 2009 3:50 pm
15. Working alone, R can complete a certain kind of job in 9 hours. R and S, working together at their respective rates, can complete one of these jobs in 6 hours. In how many hours can S, working alone, complete one of these jobs?
(A) 18 (B) 12 (C) 9
(D) 6 (E) 3
Thanks
Join the discussion
Source: — Problem Solving |

by syr » Wed Jun 03, 2009 5:28 pm
First of all, this should be posted in the Problem Solving (PS) section of the GMAT. This is the Data Sufficiency (DS) section

Here is the explanation --

Given, R can complete the job in 9hrs.
Therefore, in 1 hr he can complete 1/9th of the job. This is basically his rate.

R -> 1/9 th of work in 1 hr

Given, R + S can complete the same job in 6hrs.
Therefore, in 1hr they can complete 1/6th of the job. This is the rate for both R and S working together.

So, if we find the rate at which S works, we can determine the number of hrs he requires for the job.

Rate of S = Rate of (R + S) - Rate of R
= 1/6 - 1/9
= 1/18

Thus S's rate is 1/18. ie he can complete 1/18 of work in 1 hr
Thus, he will take 18 hrs to complete the whole job.

Answer is A)18

HTH
Join the discussion

by anoop.dimri » Wed Feb 06, 2013 11:45 am
R*9=(R+S)*6
R=2S
Work done by R is performed in such hours, and S requires double (2) time to complete the same work
Join the discussion

by Brent@GMATPrepNow » Wed Feb 06, 2013 11:56 am
ramonsa wrote:15. Working alone, R can complete a certain kind of job in 9 hours. R and S, working together at their respective rates, can complete one of these jobs in 6 hours. In how many hours can S, working alone, complete one of these jobs?
(A) 18
(B) 12
(C) 9
(D) 6
(E) 3
Let's assign a "nice" value to the job.
Say, the job is to make 18 widgets (since 9 and 6 both divide nicely into 18).

R can complete the job in 9 hours
In other words, R can make 18 widgets in 9 hours.
This means that machine R's rate is 2 widgets/hour

Together, R and S can complete the job in 6 hours
In other words, R+S can make 18 widgets in 6 hours.
This means their combined rate is 3 widgets/hour

So, working along, Machine S's rate must be 1 widget/hour.

In how many hours can S, working alone, complete one of these jobs?
So, machine S must make 18 widgets, and its rate is 1 widget/hour.
So, it will take 18 hours

Answer: A

Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com