The following problem appeared on my MGMAT CAT. MGMAT only uses the plugging in method for this problem. However, I would like to see an algebraic solution.
Machine A can complete a certain job in x hours. Machine B can complete the same job in y hours. If A and B work together at their respective rates to complete the job, which of the following represents the fraction of the job that B will not have to complete because of A's help?
A) x - y/x + y
B) x/y - x
C) x + y/xy
D) y/x - y
E) y/x + y
Machine A can complete a certain job in x hours. Machine B can complete the same job in y hours. If A and B work together at their respective rates to complete the job, which of the following represents the fraction of the job that B will not have to complete because of A's help?
A) x - y/x + y
B) x/y - x
C) x + y/xy
D) y/x - y
E) y/x + y