BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Matt and Peter can do together a piece of work in 20 days...

Expert replies
by swerve » Mon Dec 11, 2017 6:49 am
Matt and Peter can do together a piece of work in 20 days. After they have worked together for 12 days Matt stops and Peter completes the remaining work in 10 days. In how many days Peter complete the work separately ?

A. 26 days
B. 27 days
C. 23 days
D. 25 days
E. 24 days

The OA is D.

Please, can any expert explain this PS question for me? I have many difficulties to understand why that is the correct answer. Thanks.
Join the discussion
Source: — Problem Solving |

by Jay@ManhattanReview » Mon Dec 11, 2017 7:07 am
swerve wrote:Matt and Peter can do together a piece of work in 20 days. After they have worked together for 12 days Matt stops and Peter completes the remaining work in 10 days. In how many days Peter complete the work separately ?

A. 26 days
B. 27 days
C. 23 days
D. 25 days
E. 24 days

The OA is D.

Please, can any expert explain this PS question for me? I have many difficulties to understand why that is the correct answer. Thanks.
Say Matt alone completes the work in m day, and Peter alone completes the work in p day.

Thus, Matt's one day work = 1/m and Peter's one day work = 1/p

=> One day work of Matt and Peter = 1/m + 1/p = 1/20

12-day work of Matt and Peter = 12/20 = 3/5

Work remaining = 1 - 3/5 = 2/5

We know that Peter alone does the 2/5th of work in 10 days, thus 10/p = 2/5 => p = 25 days.

The correct answer: D

Hope this helps!

-Jay
_________________
Manhattan Review GMAT Prep

Locations: Stamford | Istanbul | Evanston | Seoul | and many more...

Schedule your free consultation with an experienced GMAT Prep Advisor! Click here.
Join the discussion

by GMATWisdom » Mon Dec 11, 2017 8:04 am
swerve wrote:Matt and Peter can do together a piece of work in 20 days. After they have worked together for 12 days Matt stops and Peter completes the remaining work in 10 days. In how many days Peter complete the work separately ?

A. 26 days
B. 27 days
C. 23 days
D. 25 days
E. 24 days

The OA is D.

Please, can any expert explain this PS question for me? I have many difficulties to understand why that is the correct answer. Thanks.
Both can finish the one work in 20 days means their one days work is 1/20th work
in 12 days together they will complete 12/20=3/5 th work
remaining is 1-(3/5) = 2/5 th work
this 2/5 th work Peter completes in 10 days
therefore Peter would do the complete work in 10*(5/2) =25 days
Hence D is the correct option
Join the discussion

by Scott@TargetTestPrep » Fri Sep 27, 2019 7:35 am
swerve wrote:Matt and Peter can do together a piece of work in 20 days. After they have worked together for 12 days Matt stops and Peter completes the remaining work in 10 days. In how many days Peter complete the work separately ?

A. 26 days
B. 27 days
C. 23 days
D. 25 days
E. 24 days

The OA is D.

Please, can any expert explain this PS question for me? I have many difficulties to understand why that is the correct answer. Thanks.
We can let m and p be the number of days it takes Matt and Peter to complete the work independently and separately. So we have Matt's rate = 1/m and Peter's rate = 1/p. We can create the equations:

20(1/m + 1/p) = 1

and

12(1/m + 1/p) + 10(1/p) = 1

Dividing the first equation by 20, we have 1/m + 1/p = 1/20. Now, substituting 1/20 for (1/m + 1/p) in the second equation, we have:

12(1/20) + 10/p = 1

3/5 + 10/p = 1

10/p = 2/5

2p = 50

p = 25

Alternate Solution:

Since the job takes 20 days to complete by both of them working together, then in 12 days, 12/20 = 3/5 of the job is completed, and 1 - 3/5 = 2/5 of the job is left to be completed by Peter alone. We are given that Peter can complete 2/5 of the job in 10 days; therefore, Peter would complete 1/1 of the job in 10/(2/5) = 25 days.

Answer: D

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage
Join the discussion