BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Percents

Expert replies
by Nightmare » Wed May 08, 2013 10:38 am
A,B,C can do a piece of work in 36,54,and 72 days respectively. they started the work but A left 8 days before the completion of the work while B left 12 days before the completion. the number of days for which c worked is?
Join the discussion
Source: — Problem Solving |

by ygdrasil24 » Wed May 08, 2013 10:55 am
You may find number of approaches for such questions. I personally find below method to be shortest.
A=36
B=24
C=72.

Take LCM of these numbers to get 18X12.
So A will finish 18X12/36=6 units in 1 day, similarly B=4 units, C=3 units.
Let total work to be completed is 18X12(This is imp number to choose)
Let C worked for x days
so A worked for x-8, B for x-12, C for x
so A's Rate X Days Worked + .... = total work
6(x-8)+4(x-12)+3x=18X12, solve for x to get 24.

I know this method works well, but I have a general question , is it OK to assume two values in one linear equation, here we assumed, 18X 12 and x, had it been ratio or similar, the assumed expression might have got canceled.Please comment.
Join the discussion

by Atekihcan » Wed May 08, 2013 11:22 am
In one day,
  • A does 1/36 of the work
    B does 1/54 of the work
    C does 1/72 of the work

    Together all three of them does (1/36 + 1/54 + 1/72) = (1/18)*(1/2 + 1/3 + 1/4) = (1/18)*(6 + 4 + 3)/12 = 13/12*18
A and C together worked for (12 - 8) = 4 days.
In these 4 days, they completed 4*(1/36 + 1/72) = 4*(2/72 + 1/72) = 4*3/72 = 12/72 of the work

C alone worked for 8 days.
In these 8 days, C completed 8/72 of the work.

So, in last 12 days (12/72 + 8/72) = 20/72 of the work was done.
Hence, the rest of the work, i.e. (1 - 20/72) = 52/72 of the work was done by all of the together.

Now, all of the together takes 12*18/13 days to complete the job.
So, they will take (12*18/13)*(52/72) = 12 days to complete 52/72 of the work.

So, C worked for (12 + 12) = 24 days.
Join the discussion