BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Engineer/Work Problem

Expert replies
by knight247 » Sat Jan 19, 2013 3:30 am
An engineer undertakes a project to build a road 15 KM long in 300 days and employs 45 men for the purpose. After 100 days, he finds only 2.5 KM of the road has been completed. Find the number of extra men he must employ to finish the work in time.

(A)43
(B)46
(C)55
(D)68
(E)60

No OA. Detailed explanations would be appreciated. Thanks
Join the discussion
Source: — Problem Solving |

by GMATGuruNY » Sat Jan 19, 2013 4:32 am
knight247 wrote:An engineer undertakes a project to build a road 15 KM long in 300 days and employs 45 men for the purpose. After 100 days, he finds only 2.5 KM of the road has been completed. Find the number of extra men he must employ to finish the work in time.

(A)43
(B)46
(C)55
(D)68
(E)60

No OA. Detailed explanations would be appreciated. Thanks
(men)(days) / work = (men)(days) / work.

Here is the reasoning behind the proportion above:
A certain number of MEN working for a certain number of DAYS (the numerator) are equivalent to a certain amount of WORK (the denominator)..

In 100 days, 45 men complete 2.5 kilometers.
The road is to be 15 kilometers and must be completed in 300 days total.
We need to determine how many men are needed to complete the remaining 12.5 kilometers in 200 days.
Thus:
(45)(100) / 2.5 = (x)(200) / 12.5
1800 = 16x
x = 112.5.

Since the number of men must be an integer value, the total number of men needed = 113.
Thus, the number of ADDITIONAL men needed = 113-45 = 68.

The correct answer is D.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.