If 12 men and 16 women can do a piece of work in 5 days and

This topic has 4 expert replies and 0 member replies

If 12 men and 16 women can do a piece of work in 5 days and

Post

Timer

00:00

Your Answer

A

B

C

D

E

Global Stats

Difficult



Source: GMAT Prep

If 12 men and 16 women can do a piece of work in 5 days and 13 men and 24 women can do it in 4 days, how long will 7 men and 10 women take to do it?

A. 4.2 days
B. 6.8 days
C. 8.3 days
D. 9.8 days
E. 10.2 days

The OA is C.

  • +1 Upvote Post
  • Quote
  • Flag

GMAT/MBA Expert

Post
BTGmoderatorLU wrote:
Source: GMAT Prep

If 12 men and 16 women can do a piece of work in 5 days and 13 men and 24 women can do it in 4 days, how long will 7 men and 10 women take to do it?

A. 4.2 days
B. 6.8 days
C. 8.3 days
D. 9.8 days
E. 10.2 days

The OA is C.
Let M = the rate for each man and W = the rate for each woman.

The TIME RATIO for 12 men and 16 women to 13 men and 24 women is 5 days to 4 days.
Since time and rate are RECIPROCALS, the RATE RATIO for 12M+16W and 13M+24W is equal to the reciprocal of the time ratio:
(12M+16W)/(13M+24W) = 4/5
60M + 80W = 52M + 96W
8M = 16W
M = 2W.

Let W = 1 widget per day, implying that M = 2 widgets per day.

Work produced each day by 12 men and 16 women = (12*2) + (16*1) = 40 widgets per day.
Thus, the total work produced by 12 men and 16 women over 5 days = 40*5 = 200 widgets.

Work produced each day by 7 men and 10 women = (7*2) + (10*1) = 24 widgets per day.
Time for 7 men and 10 women to produce 200 widgets = 200/24 = 25/3 ⩳ 8.3 days.

The correct answer is C.

I doubt that this problem is contained in GMATPrep.
While the question stem asks for an exact time, the OA is an approximation.
The GMAT does not use the phrase "piece of work."
Also, it seems sexist for the men's rate to be twice the women's rate.
The GMAT strives to avoid this sort of bias.

_________________
Mitch Hunt
Private Tutor for the GMAT and GRE
GMATGuruNY@gmail.com

If you find one of my posts helpful, please take a moment to click on the "UPVOTE" icon.

Available for tutoring in NYC and long-distance.
For more information, please email me at GMATGuruNY@gmail.com.
Student Review #1
Student Review #2
Student Review #3

  • +1 Upvote Post
  • Quote
  • Flag
Free GMAT Practice Test How can you improve your test score if you don't know your baseline score? Take a free online practice exam. Get started on achieving your dream score today! Sign up now.

GMAT/MBA Expert

Post
BTGmoderatorLU wrote:
Source: GMAT Prep

If 12 men and 16 women can do a piece of work in 5 days and 13 men and 24 women can do it in 4 days, how long will 7 men and 10 women take to do it?

A. 4.2 days
B. 6.8 days
C. 8.3 days
D. 9.8 days
E. 10.2 days
We can let the time it takes 1 man to finish the work = m, and thus the rate of 1 man = 1/m. Likewise, we can let the time it takes 1 woman to finish the work = w, and thus the rate of 1 woman = 1/w.

Thus, the combined rate of 12 men and 16 women is 12/m + 16/w. Since they can finish the work in 5 days, their combined rate is also equal to 1/5. Thus, we have:

12/m + 16/w = 1/5

Multiplying both sides of the equation by 5mw, we have:

60w + 80m = mw

Similarly, the combined rate of 13 men and 24 women is 13/m + 24/w. Since they can finish the work in 4 days, their combined rate is equal to 1/4. Thus, we have:

13/m + 24/w = 1/4

Multiplying both sides of the equation by 4mw, we have:

52w + 96m = mw

So, we have 60w + 80m = 52w + 96m (since they both equal mw).

60w + 80m = 52w + 96m

8w = 16m

w = 2m

We can now substitute w = 2m into the first equation, 12/m + 16/w = 1/5, to solve for m:

12/m + 16/(2m) = 1/5

12/m + 8/m = 1/5

20/m = 1/5

m = 100

Since m = 100 days, w = 200 days. The rate of 1 man is 1/100 and the rate of 1 woman is 1/200. Thus, the rate of 7 men and 10 women is 7/100 + 10/200 = 7/100 + 5/100 = 12/100, and the time for them to finish the same work is 1/(12/100) = 100/12 = 8.3 days.

Alternate Solution:

Alternatively, we can interpret the equation w = 2m as follows:

The time required for 1 woman to finish the job is twice that of a man; or in other words, the job done by 2 women is equivalent to the job done by 1 man. We know 12 men and 16 women finish the job in 5 days and as per the above discussion, this is equivalent to the job done by 12 + 16/2 = 20 men.

The question is asking for the time required to finish the job with 7 men and 10 women working, which is equivalent to 7 + 10/2 = 12 men working. We can set up an inverse proportion to find the required time: If 20 men finish a job in 5 days, then 12 men finish the job in how many days? Letting this unknown quantity be x, we have

20*5 = 12*x

x = 100/12 = 8.3 days

Answer: C

_________________
Scott Woodbury-Stewart Founder and CEO

  • +1 Upvote Post
  • Quote
  • Flag
Post
BTGmoderatorLU wrote:
Source: GMAT Prep

If 12 men and 16 women can do a piece of work in 5 days and 13 men and 24 women can do it in 4 days, how long will 7 men and 10 women take to do it?

A. 4.2 days
B. 6.8 days
C. 8.3 days
D. 9.8 days
E. 10.2 days
\[7\,\,{\text{men}}\,\, \cup \,\,\,{\text{10}}\,\,{\text{women}}\,\,\, - \,\,\,1\,\,{\text{work}}\,\,\,\, - \,\,\,?\,\,{\text{days}}\]

Is there a systematic way of dealing with this kind of problem, to be able to do it in a few minutes "naturally"?

Certainly! Let´s do it:

Let "task" be the fraction of this (piece of) work that one man can do in 1 day, hence:

\[1\,\,{\text{man}}\,\,\, - \,\,\,1\,\,{\text{day}}\,\,\,\, - \,\,\,1\,\,{\text{task}}\]

Let k (k>0) be the fraction of the "task" defined above that one woman can do in 1 day (where k may be between 0 and 1, or equal to 1, or greater), hence:

\[1\,\,{\text{woman}}\,\,\, - \,\,\,1\,\,{\text{day}}\,\,\, - k\,\,{\text{tasks}}\,\]

Now the long-lasting benefit of this "structure": everything else becomes easy and "automatic":

\[\left. \begin{gathered}
{\text{12}}\,\,{\text{men}} - \,\,\,5\,\,{\text{days}}\,\,\, - \,\,\,\,12 \cdot \,5 \cdot 1\,\,\,{\text{tasks}}\, \hfill \\
{\text{16}}\,\,{\text{women}} - \,\,\,5\,\,{\text{days}}\,\,\, - \,\,\,\,16 \cdot \,5 \cdot k\,\,\,{\text{tasks}}\,\,\, \hfill \\
\end{gathered} \right\}\,\,\,\,\,\mathop \Rightarrow \limits^{{\text{question}}\,\,{\text{stem}}} \,\,\,\,5\left( {12 + 16k} \right)\,\,{\text{tasks}}\,\,\,\, = \,\,\,\,1\,\,{\text{work}}\,\,\,\,\left( * \right)\]
\[\left. \begin{gathered}
{\text{13}}\,\,{\text{men}} - \,\,\,4\,\,{\text{days}}\,\,\, - \,\,\,\,13 \cdot \,4 \cdot 1\,\,\,{\text{tasks}}\, \hfill \\
{\text{24}}\,\,{\text{women}} - \,\,\,4\,\,{\text{days}}\,\,\, - \,\,\,\,24 \cdot \,4 \cdot k\,\,\,{\text{tasks}}\,\,\, \hfill \\
\end{gathered} \right\}\,\,\,\,\,\mathop \Rightarrow \limits^{{\text{question}}\,\,{\text{stem}}} \,\,\,\,4\left( {13 + 24k} \right)\,\,{\text{tasks}}\,\,\,\, = \,\,\,\,1\,\,{\text{work}}\,\,\,\,\left( {**} \right)\]

\[\left( * \right) = \left( {**} \right)\,\,\,\,\,\, \Rightarrow \,\,\,\,\,5\left( {12 + 16k} \right) = 4\left( {13 + 24k} \right)\,\,\,\,\, \Rightarrow \,\,\,\,\,k = \frac{1}{2}\]
\[?\,\,\,\,:\,\,\,\,\,\left. \begin{gathered}
\boxed{{\text{7}}\,\,{\text{men}}} - \,\,\,1\,\,{\text{day}}\,\,\, - \,\,\,\,7\,\,\,{\text{tasks}}\, \hfill \\
\boxed{{\text{10}}\,\,{\text{women}}} - \,\,\,1\,\,{\text{day}}\,\,\, - \,\,\,\,10 \cdot k = 5\,\,\,{\text{tasks}}\,\,\, \hfill \\
\end{gathered} \right\}\,\,\,\,\,\mathop \Rightarrow \limits^{\boxed{{\text{FOCUSED - GROUP}}}} \,\,\,\,\frac{{12\,\,{\text{tasks}}}}{{1\,\,\,{\text{day}}}}\,\,\,\,\left( {***} \right)\]

\[\left( * \right)\,\,\,\,\, \Rightarrow \,\,\,\,\,5\left( {12 + 16 \cdot \frac{1}{2}} \right) = 100\,\,{\text{tasks}}\,\,{\text{ = }}\,\,{\text{1}}\,\,{\text{work}}\,\]

And we finish in "high style", using UNITS CONTROL, one of the most powerful tools of our method!

\[\left( {***} \right)\,\,\,\,?\,\,\, = \,\,\,100\,\,{\text{tasks}}\,\,\,\,\left( {\frac{{1\,\,\,\,{\text{day}}}}{{12\,\,{\text{tasks}}}}\begin{array}{*{20}{c}}
\nearrow \\
\nearrow
\end{array}} \right)\,\,\,\, = \,\,\,\,\frac{{100}}{{12}} = \frac{{25}}{3} = \frac{{24 + 1}}{3} = 8\frac{1}{3}\,\,\,\,\left[ {{\text{days}}} \right]\]
Obs.: arrows indicate licit converter.


This solution follows the notations and rationale taught in the GMATH method.

Regards,
fskilnik.

_________________
Fabio Skilnik :: https://GMATH.net (Math for the GMAT) or https://GMATH.com.br (Portuguese version)
Course release PROMO : finish our test drive till 30/Dec with (at least) 50 correct answers out of 92 (12-questions Mock included) to gain a 50% discount!

  • +1 Upvote Post
  • Quote
  • Flag

GMAT/MBA Expert

Post
Hi All,

We're told that 12 men and 16 women can do a piece of work in 5 days and 13 men and 24 women can do it in 4 days. We're asked how long it will take 7 men and 10 women to complete that same task. This question can be approached in a couple of different ways (some of which involve a lot of calculations). The answer choices are sufficiently 'spread out' that you can use a bit of 'ratio math' and a little logic to get to the correct answer.

We're going to focus on just the first piece of information: it takes 12 men and 16 women a total of 5 days to complete a task. If you were to DOUBLE the number of workers, then you would HALVE the amount of time (re: 24 men and 32 women would take 2.5 days to complete the task). If you were to HALVE the number of workers, then you would DOUBLE the amount of time that it takes to complete the task:

6 men and 8 women would take a total of 10 days to complete a task.

If we HALVE the number of workers again, we would again DOUBLE the amount of time needed to complete the task:

3 men and 4 women would take a total of 20 days to complete a task.

We're asked how long it would take 7 men and 10 women to complete that task. If we multiply the above 'work information' by 2.5, we get...

(2.5)(3) men and (2.5)(4 women) would take a total of 20/2.5 days to complete a task...
7.5 men and 10 women would take a total of 8 days to complete a task.
Notice how this is almost the exact question we were asked to solve for. The difference is that we're including an extra "1/2 of a man" in this calculation. With just 7 men (instead of 7.5 men), we would need slightly more than 8 days to complete the task. There's only one answer that matches....

Final Answer: C

GMAT assassins aren't born, they're made,
Rich

_________________
Contact Rich at Rich.C@empowergmat.com

  • +1 Upvote Post
  • Quote
  • Flag
  • Magoosh
    Magoosh
    Study with Magoosh GMAT prep

    Available with Beat the GMAT members only code

    MORE DETAILS
    Magoosh
  • Economist Test Prep
    Free Trial & Practice Exam
    BEAT THE GMAT EXCLUSIVE

    Available with Beat the GMAT members only code

    MORE DETAILS
    Economist Test Prep
  • Veritas Prep
    Free Veritas GMAT Class
    Experience Lesson 1 Live Free

    Available with Beat the GMAT members only code

    MORE DETAILS
    Veritas Prep
  • The Princeton Review
    FREE GMAT Exam
    Know how you'd score today for $0

    Available with Beat the GMAT members only code

    MORE DETAILS
    The Princeton Review
  • e-gmat Exclusive Offer
    Get 300+ Practice Questions
    25 Video lessons and 6 Webinars for FREE

    Available with Beat the GMAT members only code

    MORE DETAILS
    e-gmat Exclusive Offer
  • Target Test Prep
    5-Day Free Trial
    5-day free, full-access trial TTP Quant

    Available with Beat the GMAT members only code

    MORE DETAILS
    Target Test Prep
  • EMPOWERgmat Slider
    1 Hour Free
    BEAT THE GMAT EXCLUSIVE

    Available with Beat the GMAT members only code

    MORE DETAILS
    EMPOWERgmat Slider
  • PrepScholar GMAT
    5 Day FREE Trial
    Study Smarter, Not Harder

    Available with Beat the GMAT members only code

    MORE DETAILS
    PrepScholar GMAT
  • Varsity Tutors
    Award-winning private GMAT tutoring
    Register now and save up to $200

    Available with Beat the GMAT members only code

    MORE DETAILS
    Varsity Tutors
  • Kaplan Test Prep
    Free Practice Test & Review
    How would you score if you took the GMAT

    Available with Beat the GMAT members only code

    MORE DETAILS
    Kaplan Test Prep

Top First Responders*

1 Brent@GMATPrepNow 65 first replies
2 fskilnik@GMATH 55 first replies
3 Jay@ManhattanReview 44 first replies
4 GMATGuruNY 34 first replies
5 Rich.C@EMPOWERgma... 32 first replies
* Only counts replies to topics started in last 30 days
See More Top Beat The GMAT Members

Most Active Experts

1 image description fskilnik@GMATH

GMATH Teacher

135 posts
2 image description Brent@GMATPrepNow

GMAT Prep Now Teacher

103 posts
3 image description Max@Math Revolution

Math Revolution