To fill an order, a manufacturer had to produce \(1000\) tools per day for \(n\) days. What is the value of \(n?\)

This topic has expert replies
Moderator
Posts: 2058
Joined: Sun Oct 29, 2017 4:24 am
Thanked: 1 times
Followed by:5 members

Timer

00:00

Your Answer

A

B

C

D

E

Global Stats

To fill an order, a manufacturer had to produce \(1000\) tools per day for \(n\) days. What is the value of \(n?\)

(1) Because of production problems, the manufacturer produced only \(600\) tools per day during the first \(5\) days.
(2) Because of production problems, the manufacturer had to produce \(1,500\) tools per day on each of the last \(4\) days in order to meet the schedule.

Answer: E

Source: GMAT Prep
Source: — Data Sufficiency |