BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Rates and Work

Expert replies
by snapplesf » Fri Mar 23, 2007 11:03 am
source - GMATPrep
--------------------------------------------

6 machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days ?

2, 3, 4, 6, 8



see answer below









Ans = 3

Is there a technique to this problem type ? Applied the standard RT=W principles, but lost on this one..

------------------------------------------------------------------
Join the discussion
Source: — Problem Solving |

by jayhawk2001 » Fri Mar 23, 2007 6:00 pm
Let x be the time it takes for 1 machine to complete the job

6 * 1/x = 1/12
x = 72 days

n machines can complete the job in 8 days, so
n * 1/72 = 1/8
n = 9

Additional machines required = 9-6 = 3 days
Join the discussion

by snapplesf » Sat Mar 24, 2007 9:12 am
thanks jayhawk2001 !
Join the discussion

by Cybermusings » Tue Mar 27, 2007 5:07 am
6 machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days ?

2, 3, 4, 6, 8

This one is easy -

6 Machines - 1 Work - 12 Days

1 Machine - 1 Work - 12 * 6 Days

x Machines - 1 Work - 12 * 6 / x Days

12 * 6 / x = 8

Therefore x = 9

Thus 9 - 6 = 3 additional machines are needed

Hope this helps
Join the discussion

by Scott@TargetTestPrep » Wed Jun 20, 2018 4:30 pm
snapplesf wrote: --------------------------------------------

6 machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days ?

2, 3, 4, 6, 8
We are given that six machines, each working at the same constant rate, together can complete a certain job in 12 days. Since rate = work/time, and if we consider work as 1, the rate of the six machines is 1/12.

We need to determine how many additional machines each working at the same constant rate will be needed to complete the same job in 8 days. In other words, we need to determine how many additional machines are needed to work at a rate of 1/8. Since each machine works at the same constant rate, we can use a proportion to first determine the number of machines needed to work at the rate of 1/8.

Our proportion is as follows: 6 machines is to a rate of 1/12 as x machines is to a rate of 1/8.

6/(1/12) = x/(1/8)

72 = 8x

x = 9

So, we need 9 - 6 = 3 more machines.

Answer: B

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage
Join the discussion