A-9000 p/hr
B-7000p/hr
let A works for a hours and B for b hours
then 9000a + 7000b = 100000
9a+7b=100
a max=8
thus to minimize b, maximize a
72 + 7b = 100
b= 4 hours
rates
This topic has expert replies
Source: Beat The GMAT — Problem Solving |
- cans
- Legendary Member
- Posts: 1309
- Joined: Mon Apr 04, 2011 5:34 am
- Location: India
- Thanked: 310 times
- Followed by:123 members
- GMAT Score:750
If my post helped you- let me know by pushing the thanks button 
Contact me about long distance tutoring!
[email protected]
Cans!!
Contact me about long distance tutoring!
[email protected]
Cans!!
- [email protected]
- Legendary Member
- Posts: 934
- Joined: Tue Nov 09, 2010 5:16 am
- Location: AAMCHI MUMBAI LOCAL
- Thanked: 63 times
- Followed by:14 members
Good Tricky sum man!!!!!1
IT IS TIME TO BEAT THE GMAT
LEARNING, APPLICATION AND TIMING IS THE FACT OF GMAT AND LIFE AS WELL... KEEP PLAYING!!!
Whenever you feel that my post really helped you to learn something new, please press on the 'THANK' button.
LEARNING, APPLICATION AND TIMING IS THE FACT OF GMAT AND LIFE AS WELL... KEEP PLAYING!!!
Whenever you feel that my post really helped you to learn something new, please press on the 'THANK' button.