BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
Live EA class + 6 months of EA OnDemand
  • Expert-led weekly online sessions
  • EA Masterclass access between classes
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

130-point score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Divide & Conquer

Expert replies
by The Apprentice » Thu Sep 10, 2009 7:47 am
Tom, working alone, can paint a room in 6 hours. Peter and John, working independently, can paint the same room in 3 hours and 2 hours, respectively. Tom starts painting the room and works on his own for one hour. He is then joined by Peter and they work together for an hour. Finally, John joins them and the three of them work together to finish the room, each one working at his respective rate. What fraction of the whole job was done by Peter?


A. 1/9
B. 1/6
C. 1/3
D. 7/18
E. 4/9

The OA is E. Can anyone explain?
Join the discussion
Source: — Problem Solving |

by bharathh » Thu Sep 10, 2009 8:04 am
The key to this question is to choose a number that you can use to denote the total amount of work.

I'm going with 18 since that is the highest number that in the answers and is divisible by 6,2,and 3

So there are 18 total units of work

Tom can finish 18 units in 6 hrs.. So he works at a rate of 3 units/hr

Peter finishes in 3 hrs .. = 6 units/hr

John finishes in 2 hrs = 9 units/hr

Now let's go on an hour by hour basis.

Hr 1 | 3 units of work done (Tom works alone)
Hr 2 | 3 + 6 units of work done (Tom + Peter)

Now at the end of hr 2 we have 12 units of work done in total.

18-12 = 6 units of work...

6 units of work will be distributed among Tom, Peter and John.

If you compare their rates of work.

T:P:J = 3:6:9 ... Peter will do 6/18th or 1/3 of the remaining 6 units = 2 units

Total work that Peter does = 6 (from hr 2) + 2 (from hr 3) = 8

So peter does 8 units out of 18 ... = 8/18 = 4/9

This is an easy problem if you choose the right number... Otherwise you will spend ages trying to figure out the answer!