If 6 workers can build 4 cars in 2 days, then how many days would it take 8 workers to build 6 cars
(A)5/3
(B)9/4
(C)8/3
(D)11/4
(E)10/3
(A)5/3
(B)9/4
(C)8/3
(D)11/4
(E)10/3
BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course
RedeemTarget Test Prep · GMAT
Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

with Chris Peckover

with Logan Thompson
Complete access from day one. Study on your schedule.
Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.
6 workers can build 4 cars in 2 days.karthikpandian19 wrote:If 6 workers can build 4 cars in 2 days, then how many days would it take 8 workers to build 6 cars
(A)5/3
(B)9/4
(C)8/3
(D)11/4
(E)10/3
Anurag@Gurome wrote:6 workers can build 4 cars in 2 days.karthikpandian19 wrote:If 6 workers can build 4 cars in 2 days, then how many days would it take 8 workers to build 6 cars
(A)5/3
(B)9/4
(C)8/3
(D)11/4
(E)10/3
1 worker can build 4 cars in 2*6 = 12 days
1 worker can build 1 car in 12/4 = 3 days
1 worker can build 6 cars in 3*6 = 18 days
8 workers can build 6 cars in 18/8 = [spoiler]9/4[/spoiler] days
The correct answer is B.
Thank you for this Anurag....
I was struggling with different time consuming, now i am ok with ur explanation