BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

a ps from gmatclub

Expert replies
by diebeatsthegmat » Sat Jul 16, 2011 7:50 pm
It takes 7 high school kids, working at the same constant rates, 10 hours to paint a certain house. At what time will the house be complete if 7 kids start painting at 9am and one kid (assume identical rates for all kids) is added per hour starting 1 pm?

A. 3 pm
B. 4:30 pm
C. 5 pm
D. 5:20 pm
E. 6:20 pm

my answer is not D and here is what i did ... can you guys please help me where i made it wrong,ok?
7 kids paint a house in 10 hours so 1 kids will paint a house in 70 hours so 8 kids will paint a house in 70/8=8.75 hours
from 9 am till 1 pm is totally 4 hours and for 4 hours 7 kids painted 2/5 house so there would be 3/5 house left
so 8 kids will paint 3/5 house in =8.75*3/5=5.25 hours....
where did i do wrong?
Join the discussion
Source: — Problem Solving |

by winniethepooh » Sat Jul 16, 2011 9:01 pm
Hi,
You haven't really understood the question well..
At 1 PM and onwards after each hour there will be an addition of 1 kid after EACH hour.
so 7 kids take 70 hours, total work needed = 70 hrs.
at 1 PM = 28 hrs
at 2 pm= + 8 hrs
at 3 pm= + 9 hrs
at 4 pm= + 10hrs
at 5 pm= + 11hrs(At this point you reach 66 hrs, you need 4 hrs to complete 70 hrs and there are now 12 kids so 4/12)
at 5:20= + 4 hrs
Total= 70Hrs
Join the discussion

by mirantdon » Sun Jul 17, 2011 2:29 am
Good question +1 for D.
I did it the other way .
4/10 of the work is done by 1 pm
The remaining work = 0.6 .
So after 1 pm = (1/10 +1/70)[ work done by 7 of them plus the additional guy(1/70)]
2 pm = (1/10 +2/70)

Keep adding values till you reach 0.6 .. Use the options as well . they are pretty far apart .!
Join the discussion

by GMATGuruNY » Sun Jul 17, 2011 4:00 am
diebeatsthegmat wrote:It takes 7 high school kids, working at the same constant rates, 10 hours to paint a certain house. At what time will the house be complete if 7 kids start painting at 9am and one kid (assume identical rates for all kids) is added per hour starting 1 pm?

A. 3 pm
B. 4:30 pm
C. 5 pm
D. 5:20 pm
E. 6:20 pm

my answer is not D and here is what i did ... can you guys please help me where i made it wrong,ok?
7 kids paint a house in 10 hours so 1 kids will paint a house in 70 hours so 8 kids will paint a house in 70/8=8.75 hours
from 9 am till 1 pm is totally 4 hours and for 4 hours 7 kids painted 2/5 house so there would be 3/5 house left
so 8 kids will paint 3/5 house in =8.75*3/5=5.25 hours....
where did i do wrong?
Let rate per kid = 1 unit per hour.
Rate of 7 kids = 7 units per hour.
Work completed over 10 hours = r*t = 7*10 = 70 units.
Work completed by 7 kids from 9am to 1pm = 7*4 = 28 units.
Remaining work = 70-28 = 42 units.
Since each kid produces 1 unit per hour, as a kid is added each hour, the amount of work produced increases by 1 unit.
Over the next 4 hours, work produced = 8+9+10+11 = 38 units.
Time is now 1pm + 4 hours = 5pm.
Remaining work = 42-38 = 4 units.
Since only 4 more units need to be produced, the work is completed between 5pm and 6pm.

The correct answer is D.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by goalevan » Sun Jul 17, 2011 7:11 am
Rate 7 kids = work/time = 1 house / 10 hours = 1/10 house/hour
Rate of 1 kid (each kid works at an equal rate) = 1/10 * 1/7 = 1/70 house/hour

For the first 4 hours, 9am - 12:59pm:
7 kids * 1/70 house/hour * 4 hours = 28/70 houses

New time: 1:00pm. Remaining work: 42/70 houses

For the next hours, 1:00-4:59pm:
8 kids * 1/70 house/hour * 1 hour = 8/70 houses
9 kids * 1/70 house/hour * 1 hour = 9/70 houses
10 kids * 1/70 house/hour * 1 hour = 10/70 houses
11 kids * 1/70 house/hour * 1 hour = 11/70 houses

New time: 4:00pm. Remaining work: 4/70 houses

12 kids * 1/70 house/hour * x hours = 4/70 houses
x = (4/70) / (12/70) = 4/12 = 1/3 hours.

Cumulative time is 4 + 1 + 1 + 1 + 1 + 1/3 hours or 8hrs:20min.

9:00am + 8hrs:20min = 5:20pm. D
Join the discussion

by diebeatsthegmat » Sun Jul 17, 2011 9:10 am
winniethepooh wrote:Hi,
You haven't really understood the question well..
At 1 PM and onwards after each hour there will be an addition of 1 kid after EACH hour.
so 7 kids take 70 hours, total work needed = 70 hrs.
at 1 PM = 28 hrs
at 2 pm= + 8 hrs
at 3 pm= + 9 hrs
at 4 pm= + 10hrs
at 5 pm= + 11hrs(At this point you reach 66 hrs, you need 4 hrs to complete 70 hrs and there are now 12 kids so 4/12)
at 5:20= + 4 hrs
Total= 70Hrs
ohh yeah i forgot reading the word "per hour". My bad!
Join the discussion

by amit2k9 » Mon Jul 18, 2011 10:05 pm
total man hours = 7*10 = 70

till 1 pm man hours = 7*4 = 28

till 5 pm man hours = 28 + 8 + 9 + 10 + 11 = 66

till 6 pm man hours = 66+12 = 78.

thus D is perfect.