Drill Press M can bore 3000 holes an hour and Drill Press N can bore 2500 holes an hour. If the two machines together must bore 45,000 holes, and if each machine can operate for at most 9 hours, what is the least amount of time, in hours, Drill Press N must operate?
A. 6
B. 7
C. 36/7
D. 8
E. 90/11
The OA is C.
I'm really confused by this PS question. Experts, any suggestion about how to solve it? Thanks in advance.