VJesus12 wrote:A carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days. How many days would it have taken the second carpenter to do the complete job working alone?
A) 4
B) 7
C) 9
D) 14
E) 24
[spoiler]OA=D[/spoiler]
Source: GMAT Paper Tests
Given that the first carpenter worked alone for 1 day on a job that would take him 6 more days to finish, the rate of the first carpenter = 1/7
Since 1-day work of the first carpenter is done, the part of work remaining = 1 - 1/7 = 6/7
Again, given that the first carpenter and the second carpenter completed the job in 4 more days, 6/7 part of the work was done by them together.
Both the carpenters , working together, would take 7/6 * 4 = 14/3 days to complete the work
Say the second carpenter, working alone, takes b days to complete the work
Thus,
1-day work of the first carpenter + 1-day work of the second carpenter = 1-day work of both the carpenters
1/7 + 1/b = 1/(14/3)
1/b = 3/14 - 1/7
b = 14 days
The correct answer:
D
Hope this helps!
-Jay
_________________
Manhattan Review GMAT Prep
Locations:
GRE Manhattan |
TOEFL Prep Courses New York |
IELTS Prep Courses Boston |
Seattle ACT Tutoring | and many more...
Schedule your free consultation with an experienced GMAT Prep Advisor!
Click here.