BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATBootcamp Starts Sep 28
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE BOOTCAMP

Live Online Bootcamp Class with Top GMAT Expert Chris Peckover

15 live classes from Sep 28, 2026

Schedule
Mon to Fri · 7:00 to 10:00 PM ET
Included
Live classes + 6 months of TTP OnDemand
  • Boost your GMAT score in less than one month in a live online class
  • 6 months access to TTP OnDemand video courses included
View bootcamp & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Digging a canal

Expert replies
by mdavis » Tue Jan 27, 2009 7:30 pm
Could someone explain how to tackle this problem step by step? I keep missing these types of problems and don't know what I am doing wrong. Thanks!

160 men can dig 3200 m of a canal in 12 days. How many men are required to dig 3600 m more of canal in 8 days?

A) 213
B) 144
C) 270
D) 225
E) 175
Join the discussion
Source: — Problem Solving |

by Zipper » Tue Jan 27, 2009 8:49 pm
https://www.facebook.com/video/video.php ... 0470751740

watch this video and try for yourself

as you said you have trouble with this kinds of problem i think the video will help you learn a nice method.

g2g no time to try to solve this :)

btw the other videos in this group are also quite nice.
Join the discussion

Re: Digging a canal

by farmanetawah » Tue Jan 27, 2009 9:06 pm
mdavis wrote:Could someone explain how to tackle this problem step by step? I keep missing these types of problems and don't know what I am doing wrong. Thanks!

160 men can dig 3200 m of a canal in 12 days. How many men are required to dig 3600 m more of canal in 8 days?

A) 213
B) 144
C) 270
D) 225
E) 175
so we can make it simple like this
160 men dig 3200 so
1 men dig 3200/160=20 m in 12 days
so in one day one man dig 20/12 m so
suppose x men are required to dig 3600m in one day
x=3600/ 20/12=3600*12/20=180*12 =2160
so for 8 day
2160/8=270
so c is coreect answ
Join the discussion

Re: Digging a canal

by gaggleofgirls » Tue Jan 27, 2009 9:39 pm
farmanetawah wrote: so we can make it simple like this
160 men dig 3200 so
1 men dig 3200/160=20 m in 12 days
so in one day one man dig 20/12 m so
suppose x men are required to dig 3600m in one day
x=3600/ 20/12=3600*12/20=180*12 =2160
so for 8 day
2160/8=270
so c is coreect answ
I like to look at it this way also because once you get the rate per person per day (or per machine per hour or per 1 worker per 1 time period) then you can take that anywhere.

With the above example you can also take a sec to reduce the fractions so the math is a bit easier.

20/12 = 5/3
rate = 5/3, we know the time = 8 days so 8*5/3 = 40/3
so 40/3 * x = 3600
x = 3600 * 3/40
x = 90 * 3 = 270

Answer = C

-Carrie
Join the discussion

by mdavis » Wed Jan 28, 2009 7:56 am
Thanks so much for the help!
Join the discussion