nidhis.1408 wrote:It takes the average dryer 80 minutes to dry one full load of Bob's laundry. Bob has one average dryer, and also decides to try one "Super Jumbo-Iron Dryer-Matic", which is faster than the average dryer by a ratio of 5 : 4. Bob has three loads of laundry, and both machines are so precise that he can set them to the minute. How many minutes does it take for him to dry his three loads? (Assume that no time passes between loads and that he can use both machines concurrently. Assume also that he never runs a machine with less than a full load. Finally, assume that Bob does not partially dry a load in one machine and then switch it to the other.)
Kindly explain the solution . Its a problem from Manhattan word translation guide.
Since the rate ratio = 5:4, let the rate of the fast machine = 5 units per minute and the rate of the slow machine = 4 units per minute.
Since the slow machine completes one load in 80 minutes, one load = r*t = 4*80 = 320 units.
Time for the fast machine to complete 320 units = w/r = 320/5 = 64 minutes.
Thus, the fast machine can complete 2 loads in 128 minutes -- more than enough time for the slow machine to complete 1 load.
Thus, the 3 loads will be completed in 128 minutes.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.
As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.
For more information, please email me (Mitch Hunt) at
[email protected].
Student Review #1
Student Review #2
Student Review #3