On Monday morning a certain machine ran continuously at a uniform rate to fill a production order. At what time did it completely fill the order that morning?
(1) The machine began filling the order at 9:30 a.m.
(2) The machine had filled 1/2 of the order by 10:30 a.m. and 5/6 to the order by 11:10 a.m.
Answer: B
Source: Official Guide
(1) The machine began filling the order at 9:30 a.m.
(2) The machine had filled 1/2 of the order by 10:30 a.m. and 5/6 to the order by 11:10 a.m.
Answer: B
Source: Official Guide