Ali and Moe can do a certain job together in 4 hours and Ali is 5 times faster than Moe. If Ali does the job by himself, how long does it take him to complete the job working at the same rate?
A. 3 hours and 20 minutes.
B. 4 hours and 12 minutes.
C. 4 hours and 48 minutes.
D. 5 hours.
E. 5 hours and 20 minutes.
The OA is C.
Moe's speed = s
Ali's speed = 5s
Then, if both working together, the combined speed will be, 6s, right?
Now, at a rate of 6s, they complete the job in 4 hours. I know that the total work will be, work = speed * time = 6s * 4 = 24s.
Then I need to determine the time that will take Ali to complete the job working alone, at the same rate.
Time = work / speed = 24s / 5s =24/5 hours or 4 hours and 48 minutes.
Please, can any expert explain this PS question for me? I would like to know how to solve it in less than 2 minutes. I need your help. Thanks.
A. 3 hours and 20 minutes.
B. 4 hours and 12 minutes.
C. 4 hours and 48 minutes.
D. 5 hours.
E. 5 hours and 20 minutes.
The OA is C.
Moe's speed = s
Ali's speed = 5s
Then, if both working together, the combined speed will be, 6s, right?
Now, at a rate of 6s, they complete the job in 4 hours. I know that the total work will be, work = speed * time = 6s * 4 = 24s.
Then I need to determine the time that will take Ali to complete the job working alone, at the same rate.
Time = work / speed = 24s / 5s =24/5 hours or 4 hours and 48 minutes.
Please, can any expert explain this PS question for me? I would like to know how to solve it in less than 2 minutes. I need your help. Thanks.