BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work Problem

Expert replies
by jnellaz » Fri Nov 21, 2008 7:46 am
A union decided to build a home. The job can be done by 3 skilled workmen in 20 days or by 5 of the novice workers in 30 days. How many days will it take if all work together?

[spoiler]Answer: 12 days[/spoiler]

Pretty straightforward but I messed this one up by doing:

5/30 + 3/20 = 1
10/60 + 9/60 = 1
19/60 = 1 or 60/19 WRONG!
Join the discussion
Source: — Problem Solving |

Re: Work Problem

by logitech » Fri Nov 21, 2008 8:16 am
jnellaz wrote:A union decided to build a home. The job can be done by 3 skilled workmen in 20 days or by 5 of the novice workers in 30 days. How many days will it take if all work together?

[spoiler]Answer: 12 days[/spoiler]

Pretty straightforward but I messed this one up by doing:

5/30 + 3/20 = 1
10/60 + 9/60 = 1
19/60 = 1 or 60/19 WRONG!
Let me try to give you a different approach.

Think the people as cars traveling with different velocities and the job done as distance, and the time to complete the job as the traveling time:

The job can be done by 3 skilled workmen in 20 days or by 5 of the novice workers in 30 days.

3S 20Days
5N 30 Days

so lets find the distance:

3Sx20days = 60Sdays

5Nx30days = 150Ndays

now remember they both travelled the same distance

60Sdays = 150Ndays

2S=5N

How many days will it take if all work together?

It actually means how long does it take for them to travel this distance if their velocities are added together!

we know the distance 150Ndays or 60Sdays ( SAME DISTANCE )

so lets pick one of them

60Sdays / (5N+3S) = ANSWER

60Sdays / ( 2S+3S) Remember 5N=2S

60Sdays / 5S

12 days! 8)

If you practice this method, you will find yourself doing this type of questions and many others VERY FAST!
LGTCH
---------------------
"DON'T LET ANYONE STEAL YOUR DREAM!"
Join the discussion

Re: Work Problem

by logitech » Fri Nov 21, 2008 8:22 am
jnellaz wrote:A union decided to build a home. The job can be done by 3 skilled workmen in 20 days or by 5 of the novice workers in 30 days. How many days will it take if all work together?

[spoiler]Answer: 12 days[/spoiler]

Pretty straightforward but I messed this one up by doing:

5/30 + 3/20 = 1
10/60 + 9/60 = 1
19/60 = 1 or 60/19 WRONG!
but if you want to do with your method:

5N 30 days so 1 N 150 days
3S 20 days so 1 S 60 days

5(1/150) + 3(1/60) = 1/X

1/30 + 1/20 = 1/X

X = 12

OR METHOD III

And this is where you get confused

Think of 3 skilled workmen and 5 of the novice workers AS ONE COMBINED WORK UNIT, because they will work again together so

3s 20 days
5N 30 days

together ?

1/20 + 1/30 = 1/x

x = 12! :D
LGTCH
---------------------
"DON'T LET ANYONE STEAL YOUR DREAM!"
Join the discussion

by jnellaz » Fri Nov 21, 2008 9:18 am
Dude, thanks again! I think you and I relate to this question. (Skilled worker versus novice)
Join the discussion

by raunekk » Fri Nov 21, 2008 9:40 am
lets find the work done per day,

3 workmen takes 20 days= 1/20 th of work/day

5 workmen takes 30 days = 1/30th of work / day

wen work together= 1/20 + 1/30 th of work / day

= 1/12 th of work /day
= 12 days of total work

thanks
Join the discussion

by cramya » Fri Nov 21, 2008 9:54 am
3 workers take 20 days 1 workers takes 60 days
5 workers take 30 days 1 woker takes 150 days

1/60 this is for 1 workers but since 3 workers are working it will be
1/60+1/60+1/60 or 3*1/60 = 1/20)


1/150 - this is for 1 worker but since 5 workers are working it will be
1/150 +1/150 +1/150 +1/150 +1/150 or 5*1/150 = 1/30)


When they work together u add the rates

rate*time = work

1/20+1/30 * t = 1
t=60/5 = 12 days
Join the discussion

by jnellaz » Fri Nov 21, 2008 10:05 am
Wow...it seems the number of ways is endless. Thanks to you both! Cramya, great illustration!
Join the discussion

by jaybrium » Fri Nov 21, 2008 10:37 am
I used the work formula:

if
a = the time it takes "a" to perform a task independently
and
b = the time it take "b" to perform the same task independently

then

ab / a + b = the time it takes both parties working together to perform "the task"

therefore;

if 3 skilled workers can build a house in 20 days; and
5 novices can build a house in 30 days; working together they can pull if off in

(20*30)/(20+30) = 12 days

the work formula can also be used if more than two parties are working together, just add variables. If there are 3 parties (a,b,c) working together then the time it takes them working together is:

abc / ab + ac + bc

I'm sure you can use it for 4 or more parties, but @ that point the formula will likely make things more complicated than necessary. I've never seen a simultanious work question that invovles four parties on the GMAT though... has anyone seen such a question?
- Jay