A project scheduled to be carried out over a single fiscal year has a budget of $12,600, divided into12 equal monthly allocations. At the end of the fourth month of that fiscal year, the total amount actually spent on the project was $4,580. By how much was the project over its budget?
(A) $380
(B) $540
(C) $1,050
(D) $1,380
(E) $1,430
Answer: A
Source: Official Guide
(A) $380
(B) $540
(C) $1,050
(D) $1,380
(E) $1,430
Answer: A
Source: Official Guide