BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

A carpenter worked alone for 1 day on a job that would take

Expert replies
by swerve » Sun Oct 20, 2019 1:14 pm
A carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days.
How many days would it have taken the second carpenter to do the complete job working alone?

A. \(4\frac{2}{3}\)
B. \(7\)
C. \(9\)
D. \(14\)
E. \(24\)

The OA is D

Source: GMAT Paper Tests
Join the discussion
Source: — Problem Solving |

by Jay@ManhattanReview » Mon Oct 21, 2019 4:24 am
swerve wrote:A carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days.
How many days would it have taken the second carpenter to do the complete job working alone?

A. \(4\frac{2}{3}\)
B. \(7\)
C. \(9\)
D. \(14\)
E. \(24\)

The OA is D

Source: GMAT Paper Tests
Given that the first carpenter worked alone for 1 day on the job that would take him 6 more days to finish, working alone, he would take 7 days to finish the work.

Say, working alone, the second carpenter takes b days to finish the work.

As per the question, the first carpenter worked alone for 1 day, and then both the carpenters worked together for 4 days.

Thus, (1/7 + 4/7) + 4/b = 1

=> b = 14 days

The correct answer: D

Hope this helps!

-Jay
_________________
Manhattan Review GMAT Prep

Locations: GMAT Classes Boston | GMAT Tutoring NYC | GRE Prep Dallas | TOEFL Prep Classes Seattle | and many more...

Schedule your free consultation with an experienced GMAT Prep Advisor! Click here.
Join the discussion

by Scott@TargetTestPrep » Wed Oct 23, 2019 5:59 pm
swerve wrote:A carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days.
How many days would it have taken the second carpenter to do the complete job working alone?

A. \(4\frac{2}{3}\)
B. \(7\)
C. \(9\)
D. \(14\)
E. \(24\)

The OA is D

Source: GMAT Paper Tests
The rate of the first carpenter is 1/7.

After the first day's work, 1/7 of the job was complete, and so the amount of work remaining to be accomplished was 6/7 of the job. The two men working together completed that remaining work (6/7 of job) in 4 days. Thus, the combined rate of the two carpenters is (6/7)/4 = 6/28 = 3/14.

Let n be the number of days it takes the second carpenter to complete the job by himself. We can create the following equation:

1/7 + 1/n = 3/14

Multiplying by 14n, we have:

2n + 14 = 3n

14 = n

Answer: D

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage
Join the discussion

swerve wrote: ↑
Sun Oct 20, 2019 1:14 pm
A carpenter worked alone for 1 day on a job that would take him 6 more days to finish. He and another carpenter completed the job in 4 more days.
How many days would it have taken the second carpenter to do the complete job working alone?

A. \(4\frac{2}{3}\)
B. \(7\)
C. \(9\)
D. \(14\)
E. \(24\)

The OA is D

Source: GMAT Paper Tests
A straightforward approach is to assign a nice value to the job.
We're looking for a number that works well with the given numbers (7 days to complete the job, and 4 extra days with help).
So let's say the carpentry job consists of making 56 wooden widgets

GIVEN: A carpenter worked alone for 1 day on a job that would take him 6 more days to finish.
This tells us that it would take the carpenter 7 days to make 56 wooden widgets
So, in ONE day, the carpenter can make 8 wooden widgets.
So, after the first day, the number of widgets we still need to make = 56 - 8 = 48

GIVEN: He and another carpenter completed the job in 4 more days.
So the two carpenters we're able to make 48 wooden widgets in 4 days
This means their COMBINED rate is 12 widgets per day
We already know that the FIRST carpenter makes 8 wooden widgets per day
This means the SECOND carpenter can make 4 wooden widgets per day.

QUESTION: How many days would it have taken the second carpenter to do the complete job working alone?
The job consists of making 56 wooden widgets
The SECOND carpenter can make 4 wooden widgets per day

time = output/rate
So, time = 56/4 = 14 days

Answer: D