BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Each type A machine fills 400 cans per minute, each Type B machine fills 600

Expert replies
by BTGModeratorVI » Sun Feb 23, 2020 7:04 am

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty—

Each type A machine fills 400 cans per minute, each Type B machine fills 600 cans per minute, and each Type C machine installs 2,400 lids per minute. A lid is installed on each can that is filled and on no can that is not filled. For a particular minute,what is the total number of machines working?

(1) A total of 4,800 cans are filled that minute
(2) For that minute, there are 2 Type B machines working for every Type C machine working

Answer: C
Source: Official Guide
Join the discussion
Source: — Data Sufficiency |

BTGModeratorVI wrote: ↑
Sun Feb 23, 2020 7:04 am
Each type A machine fills 400 cans per minute, each Type B machine fills 600 cans per minute, and each Type C machine installs 2,400 lids per minute. A lid is installed on each can that is filled and on no can that is not filled. For a particular minute,what is the total number of machines working?

(1) A total of 4,800 cans are filled that minute
(2) For that minute, there are 2 Type B machines working for every Type C machine working

Answer: C
Source: Official Guide
Given: Each type A machine fills 400 cans per minute,each Type B machine fills 600 cans per minute,and each Type C machine installs 2,400 lids per minute.A lid is installed on each can that is filled and on no can that is not filled.

Target question: For a particular minute,what is the total number of machines working?

Statement 1: A total of 4,800 cans are filled that minute
Since Machine C installs 2400 lids per second, we know that there are 2 Machine C's operating during that minute.
HOWEVER, we don't know how many Machine A's and Machine B's are working.
For example, here are two possible scenarios:
Case a: There are 12 Machine A's, 0 Machine B's and 2 Machine C's. In this case, the answer to the target question is the total number of machines working = 12 + 0 + 2 = 14
Case b: There are 0 Machine A's, 8 Machine B's and 2 Machine C's. In this case, the answer to the target question is the total number of machines working = 0 + 8 + 2 = 10
Since we cannot answer the target question with certainty, statement 1 is NOT SUFFICIENT

Statement 2: For that minute,there are 2 Type B machines working for every Type C machine working
Since we are not giving any information about how many cans are filled during the minute, statement 2 is NOT SUFFICIENT

Statements 1 and 2 combined
Statement 1 indirectly tells us that there are 2 Machine C's operating during that minute
Statement 2 indirectly tells us that there are 4 Machine B's operating during that minute (since there are 2 Type B machines working for every Type C machine working)

In one minute, 4 Machine B's can fill 2400 cans (since each Machine B can fill 600 cans per minute)
4800 - 2400 = 2400
So, the remaining 2400 cans must be filled by Machine A
Since each Machine A can fill 400 cans per minute, we'll need 6 Machine A's to fill the remaining 2400 cans.
Total number of Machines working equals = 2 + 4 + 6= 12
So, the answer to the target question is the total number of machines working = 12
Since we can answer the target question with certainty, the combined statements are SUFFICIENT

Answer: C

Cheers,
Brent