BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Together, 15 type A machines and 7 type B machines can

Expert replies
by M7MBA » Mon Apr 15, 2019 1:47 am

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty—

Together, 15 type A machines and 7 type B machines can complete a certain job in 4 hours.

Together 8 type B machines and 15 type C machines can complete the same job in 11 hours.

How many hours would it take one type A machine, one type B machine, and one type C machine working together to complete the job (assuming constant rates for each machine)?

(A) 22 hours
(B) 30 hours
(C) 44 hours
(D) 60 hours
(E) It cannot be determined from the information above.

[spoiler]OA=C[/spoiler]

Source: Veritas Prep
Join the discussion
Source: — Problem Solving |

by GMATGuruNY » Mon Apr 15, 2019 2:46 am
M7MBA wrote:Together, 15 type A machines and 7 type B machines can complete a certain job in 4 hours.

Together 8 type B machines and 15 type C machines can complete the same job in 11 hours.

How many hours would it take one type A machine, one type B machine, and one type C machine working together to complete the job (assuming constant rates for each machine)?

(A) 22 hours
(B) 30 hours
(C) 44 hours
(D) 60 hours
(E) It cannot be determined from the information above.
Let the job = 44 units.

Since 15A+7B take 4 hours to complete the 44-unit job, the rate for 15A+7B = w/t = 44/4 = 11 units per hour.
Since 8B+15C take 11 hours to complete the 44-unit job, the rate for 8B+15C = w/t = 44/11 = 4 units per hour.

Adding together 15A+7B=11 and 8B+15C=4, we get:
15A + 15B + 15C = 15 units per hour
A+B+C = 1 unit per hour
Since the rate for A+B+C = 1 unit per hour, the time for A+B+C to complete the 44-unit job = w/r = 44/1 = 44 hours.

The correct answer is C.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by Scott@TargetTestPrep » Tue Apr 16, 2019 4:57 pm
M7MBA wrote:Together, 15 type A machines and 7 type B machines can complete a certain job in 4 hours.

Together 8 type B machines and 15 type C machines can complete the same job in 11 hours.

How many hours would it take one type A machine, one type B machine, and one type C machine working together to complete the job (assuming constant rates for each machine)?

(A) 22 hours
(B) 30 hours
(C) 44 hours
(D) 60 hours
(E) It cannot be determined from the information above.

[spoiler]OA=C[/spoiler]

Source: Veritas Prep
Let a, b, and c be the times, in hours, it takes for 1 type A, B, and C machine to finish the job by itself, respectively. So we can create the equations (notice that, for example, 1/a will be the work done by 1 type A machine per hour and n/a will be the work done by n type A machines per hour):

4(15/a) + 4(7/b) = 1

and

11(8/b) + 11(15/c) = 1

If we divide the first equation by 4 and the second by 11, we have:

15/a + 7/b = 1/4

And

8/b + 15/c = 1/11

Now, adding the two new equations, we have:

15/a + 15/b + 15/c = 1/4 + 1/11

15(1/a + 1/b + 1/c) = 15/44

1/a + 1/b + 1/c = 1/44

Thus, the combined rate of 1 type A, B and C machine is 1/44. That is, together they finish 1/44 of the job in one hour. Therefore, it will take them 1/(1/44) = 44 hours to finish the job.

Answer: C