BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

A and B can complete a task in 20 days. B and C can complete

Expert replies
by BTGmoderatorLU » Wed Sep 05, 2018 1:42 pm

Timer

00:00

Answers

A

B

C

D

E

Stats

Difficulty—

Source: e-GMAT

A and B can complete a task in 20 days. B and C can complete the same task in 30 days. If A and C can complete the task in 40 days, arrange the efficiencies of A, B, and C in descending order.

A. A>B>C
B. A>C>B
C. B>A>C
D. B>C>A
E. C>A>B

The OA is C.
Join the discussion
Source: — Problem Solving |

by Jay@ManhattanReview » Wed Sep 05, 2018 8:35 pm
BTGmoderatorLU wrote:Source: e-GMAT

A and B can complete a task in 20 days. B and C can complete the same task in 30 days. If A and C can complete the task in 40 days, arrange the efficiencies of A, B, and C in descending order.

A. A>B>C
B. A>C>B
C. B>A>C
D. B>C>A
E. C>A>B

The OA is C.
We have

1. A and B can complete a task in 20 days.
2. B and C can complete the same task in 30 days.
3. A and C can complete the task in 40 days.

From (1) and (2), we see that when A is replaced by C, the number of days to complete the same task increases (30 - 20 = 10 days more). This implies that A is more efficient than C. A > C.

From (1) and (3), we see that when B is replaced by C, the number of days to complete the same task increases (40 - 20 = 20 days more). This implies that B is more efficient than C. B > C.

Similarly, From (2) and (3), we see that when B is replaced by A, the number of days to complete the same task increases (40 - 30 = 10 days more). This implies that B is more efficient than A. B > A.

From A > C, B > C, and B > A, we see that B > A > C.

The correct answer: C

Hope this helps!

-Jay
_________________
Manhattan Review

Locations: Manhattan Review Warangal | GMAT Prep Dilsukhnagar | GRE Prep Begumpet | Visakhapatnam GRE Coaching | and many more...

Schedule your free consultation with an experienced GMAT Prep Advisor! Click here.
Join the discussion

by GMATGuruNY » Thu Sep 06, 2018 4:27 am
BTGmoderatorLU wrote:Source: e-GMAT

A and B can complete a task in 20 days. B and C can complete the same task in 30 days. If A and C can complete the task in 40 days, arrange the efficiencies of A, B, and C in descending order.

A. A>B>C
B. A>C>B
C. B>A>C
D. B>C>A
E. C>A>B
Alternate approach:

Let the job = 240 units.
Since A+B take 20 days to complete the 240-unit job, A+B = 240/20 = 12 units per day.
Since B+C take 30 days to complete the 240-unit job, B+C = 240/30 = 8 units per day.
Since A+C take 40 days to complete the 240-unit job, A+C = 240/40 = 6 units per day.

Thus:

(A+B) - (B+C) = 12-8.
A-C = 4 units per day.

(A-C) + (A+C) = 4+6
2A = 10
A = 5 units per day.

Since A-C = 4 units per day, and A = 5 units per day, C = 1 unit per day.
Since B+C = 8 units per day, and C = 1 unit per day, B = 7 units per day.
Since B=7, A=5 and C=1, B>A>C.

The correct answer is C.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by Scott@TargetTestPrep » Sat Sep 29, 2018 5:09 pm
BTGmoderatorLU wrote:Source: e-GMAT

A and B can complete a task in 20 days. B and C can complete the same task in 30 days. If A and C can complete the task in 40 days, arrange the efficiencies of A, B, and C in descending order.

A. A>B>C
B. A>C>B
C. B>A>C
D. B>C>A
E. C>A>B
Since A and B can complete a task in 20 days but B and C can complete the same task in 30 days, A must be more efficient than C.

Since B and C can complete the same task in 30 days but A and C can complete the task in 40 days, B must be more efficient than A.

Therefore, their efficiencies in descending order is B, followed by A, followed by C.

Answer: C

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage
Join the discussion

by [email protected] » Sun Sep 30, 2018 3:26 pm
Hi All,

We're told that A and B can complete a task in 20 days. B and C can complete the same task in 30 days and A and C can complete the task in 40 days. We're asked to arrange the 'efficiencies' of A, B, and C in descending order. This is actually more of a 'logic question' than a 'math question' - and you can solve it with some basic logical comparisons.

To start, we know:
A and B take 20 days to do a task
B and C take 30 days to do a task
Thus, 'swapping' A for C makes the job take 10 days LONGER, meaning that A is MORE efficient than C (re: A > C).

Next, we know:
A and B take 20 days to do a task
A and C take 40 days to do a task
Thus, 'swapping' B for C makes the job take 20 days LONGER, meaning that B is MORE efficient than C (re: B > C).

Finally, we know:
B and C take 30 days to do a task
A and C take 40 days to do a task
Thus, 'swapping' B for A makes the job take 10 days LONGER, meaning that B is MORE efficient than A (re: B > A).

Combining the three inequalities, we have B > A > C

Final Answer: C

GMAT assassins aren't born, they're made,
Rich
Contact Rich at [email protected]
Image