[GMAT math practice question]

The relationship between the cost (c) and time (t) is given by the equation c=mt+b. If the time is increased by 10, by how many dollars is the cost increased?

1) m=20
2) b=30
Join the discussion
Source: — Data Sufficiency |

by GMATGuruNY » Wed Jun 27, 2018 2:29 am
Max@Math Revolution wrote:[GMAT math practice question]

The relationship between the cost (c) and time (t) is given by the equation c=mt+b. If the time is increased by 10, by how many dollars is the cost increased?

1) m=20
2) b=30
Original cost = mt+ b.
When the time increases by 10, we get:
New cost = m(t+10) + b = mt + 10m + b.
Thus:
Increase in the cost = new cost - original cost = (mt + 10m + b) - (mt + b) = 10m.
To determine the increase in the cost, we need to know the value of m.
Question stem, rephrased:
What is the value of m?

Statement 1: m=20
SUFFICIENT.

Statement 2: b=10
No information about m.
INSUFFICIENT.

The correct answer is A.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by Max@Math Revolution » Fri Jun 29, 2018 12:04 am
=>
Forget conventional ways of solving math questions. For DS problems, the VA (Variable Approach) method is the quickest and easiest way to find the answer without actually solving the problem. Remember that equal numbers of variables and independent equations ensure a solution.

The first step of the VA (Variable Approach) method is to modify the original condition and the question. We then recheck the question.

The increase in the cost when the time is increased by 10 is given by
m(t + 10) + b - (mt + b) = 10 m. As this depends on the variable m only,
condition 1) is sufficient.

Therefore, the answer is A.

Answer: A