work

This topic has expert replies
Master | Next Rank: 500 Posts
Posts: 138
Joined: Mon May 01, 2017 11:56 pm
Thanked: 4 times

work

by vaibhav101 » Sun Jun 03, 2018 10:02 am

Timer

00:00

Your Answer

A

B

C

D

E

Global Stats

A can do a work in 10 days, B in 20 days and C in 40 days. They start working in turns with A on first day, B on second day and C on third day and so on till they finish the work. Find the time taken to complete the work.

A 15.5
B 16
C 17
D 15
E 16.5
Source: — Problem Solving |

Legendary Member
Posts: 2898
Joined: Thu Sep 07, 2017 2:49 pm
Thanked: 6 times
Followed by:5 members

by Vincen » Tue Jun 05, 2018 12:28 am
vaibhav101 wrote:A can do a work in 10 days, B in 20 days and C in 40 days. They start working in turns with A on first day, B on second day and C on third day and so on till they finish the work. Find the time taken to complete the work.

A 15.5
B 16
C 17
D 15
E 16.5
Hello vaibhav101.

Here, we have to find the part of the work that each one does in one day, that is to say:

- A does a work in 10 days, then each day A does 1/10 of the work.
- B does a work in 20 days, then each day B does 1/20 of the work.
- C does a work in 40 days, then each day C does 1/40 of the work.

Since A starts, then B and finally C we can say that in three days they have done $$\frac{1}{10}+\frac{1}{20}+\frac{1}{40}=\frac{4}{40}+\frac{2}{40}+\frac{1}{40}=\frac{7}{40}\ of\ the\ work.$$ Then, in 6 days the have done $$2\left(\frac{7}{40}\right)=\frac{7}{20}\ of\ the\ work.$$ In 9 days they have done $$3\left(\frac{7}{40}\right)=\frac{21}{40}\ of\ the\ work.$$ In 12 days the have done $$4\left(\frac{7}{40}\right)=\frac{7}{10}\ of\ the\ work.$$ In 15 days the have done $$5\left(\frac{7}{40}\right)=\frac{7}{8}\ of\ the\ work.$$ Now, in 16 days the have done $$\frac{1}{10}+\frac{7}{8}=\frac{78}{80}=\frac{39}{40}\ of\ the\ work.$$ Now, we can see that left 1/40 of the work, but it is the turn of B, whose rate of work is 1/20 per day, therefore B just need to work half of the day to finish the job, because $$\frac{39}{40}+\frac{\frac{1}{20}}{2}=\frac{39}{40}+\frac{1}{40}=\frac{40}{40}=1.$$ Hence, the correct answer is the option E.

I hope it may help you.

Regards.

User avatar
GMAT Instructor
Posts: 15539
Joined: Tue May 25, 2010 12:04 pm
Location: New York, NY
Thanked: 13060 times
Followed by:1906 members
GMAT Score:790

by GMATGuruNY » Tue Jun 05, 2018 2:29 am
vaibhav101 wrote:A can do a work in 10 days, B in 20 days and C in 40 days. They start working in turns with A on first day, B on second day and C on third day and so on till they finish the work. Find the time taken to complete the work.

A 15.5
B 16
C 17
D 15
E 16.5
Let the job = 40 units.
Since A takes 10 days to complete the job, A's rate = w/t = 40/10 = 4 units per day.
Since B takes 20 days to complete the job, B's rate = w/t = 40/20 = 2 units per day.
Since C takes 40 days to complete the job, C's rate = w/t = 40/40 = 1 unit per day.
Work completed every 3 days by A+B+C = 4+2+1 = 7 units.
Since 7 units are produced every 3 days, the amount of work produced over 15 days = 5*7 = 35.
Remaining work = 40-35 = 5 units.
Since A's rate = 4 units per day, A produces on the 16th day 4 of the remaining 5 units, leaving 1 unit for B to produce on the last day.
Since B's rate = 2 units per day, B takes 1/2 day to produce the 1 remaining unit, bringing the total amount of time to 16.5 days.

The correct answer is E.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 8088
Joined: Sat Apr 25, 2015 10:56 am
Location: Los Angeles, CA
Thanked: 43 times
Followed by:29 members

by Scott@TargetTestPrep » Tue Jun 05, 2018 9:44 am
vaibhav101 wrote:A can do a work in 10 days, B in 20 days and C in 40 days. They start working in turns with A on first day, B on second day and C on third day and so on till they finish the work. Find the time taken to complete the work.

A 15.5
B 16
C 17
D 15
E 16.5
We see that in every 3 days, 1/10 + 1/20 + 1/40 = 4/40 + 2/20 + 1/40 = 7/40 of the work is completed. Therefore, in 15 days, 5 x 7/40 = 35/40 of the work will be completed. For the last 5/40 of the work, A will work on day 16, so 1/10 will be completed and 5/40 - 1/10 = 1/40 will be left undone. So B will work day 17, but he doesn't need the whole day to finish it. Since (1/40)/(1/20) = 1/2, B just needs half a day to finish the last 1/40 of the work. So the total time to complete the work is 16.5 days.

Answer: E

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage