BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Horses and Mules

Expert replies
by srcc25anu » Sat Apr 06, 2013 11:07 am
16 horses can haul a load of lumber in 24 minutes. 12 horses started hauling a load and after 14 minutes, 12 mules joined the horses. Will it take less than a quarter-hour for all of them together to finish hauling the load?

1.Mules work more slowly than horses.
2.48 mules can haul the same load of lumber in 16 minutes.

B
Join the discussion
Source: — Data Sufficiency |

by Anju@Gurome » Sat Apr 06, 2013 11:14 am
srcc25anu wrote:16 horses can haul a load of lumber in 24 minutes. 12 horses started hauling a load and after 14 minutes, 12 mules joined the horses. Will it take less than a quarter-hour for all of them together to finish hauling the load?

1. Mules work more slowly than horses.
2. 48 mules can haul the same load of lumber in 16 minutes.
The question is asking whether all of them together can finish hauling the load in 15 minutes, i.e. whether it will take 15 minutes more to finish hauling the load after 12 mules have joined.

Total work = 16*24 = 384 horse minutes
Work done by 12 horses in 14 minutes = 12*14 = 168 horse minutes.
Work left = 384 - 168 = 216 horse minutes.

Work done by 12 horses in 15 minutes = 12*15 = 180 horse minutes

Statement 1: 12 mules works slower than 12 horses, so in 15 minutes they can do less than 180 horse minutes of work. Hence, 12 horses and 12 mules together in 15 minutes can do less than (180 + 180) = 360 horse minutes of work.

But they may or may not do more than 216 horse minutes of work.

Not sufficient

Statement 2: Now we can uniquely determine the work capacity of the mules in terms of horse minutes. Hence, we can definitely answer the question in YES or NO.

Sufficient

The correct answer is B.
Last edited by Anju@Gurome on Sat Apr 06, 2013 11:28 am, edited 1 time in total.
Anju Agarwal
Quant Expert, Gurome

Backup Methods : General guide on plugging, estimation etc.
Wavy Curve Method : Solving complex inequalities in a matter of seconds.

§ GMAT with Gurome § Admissions with Gurome § Career Advising with Gurome §
Join the discussion

by srcc25anu » Sat Apr 06, 2013 11:28 am
the way i approached it: i assumed Total workload = 240 units

16 Horses - in 24 mins - 240 workload
1 horse - in 1 min - 240 / (16 * 24) = 5/8 work
12 horses - in 14 mins - 5 * 14 * 12 / 8 = 105 units completed

Left work = 240 - 105 = 135 units

we add 12 mules. suppose mules speed of work = horse work speed
1 horse can do 1 work in 8/5 mins
24 horses - can finish 135 work in 8 * 135 / (5 * 24) = 9 mins

but if mule speed < horse speed total time to complete 135 units could exceed 15 mins or maybe not. we can't know for sure. That how i approached St 1 and went for A as not sufficient.