rates and formulae.

by ildude02 » Sun Jul 13, 2008 7:37 am
A's rate is twice that of B and 1/3 that of C. They all combined to produce 2700 units, how many units did C produce?

a)300
b)600
c)900
d)1200
e)1800

My question is, I always get confused when to sum them all up and equate to the total and when we should use the formulae; 1/A +1/B +1/C = 1/T; where T is the total time, and then you derive the units based off the individual time. Can someone clarify this for me? Thanks!
Source: — Problem Solving |

Legendary Member
Posts: 1159
Joined: Wed Apr 16, 2008 10:35 pm
Thanked: 56 times

by raunekk » Sun Jul 13, 2008 8:44 am
IMO:E (1800)

IF you are given total time taken to do a job by a person or a machine,

then you need to use the formula 1/a+1/b.This will give you work done per-hour by each machine individually.That is, rate.

But if u are directly given time or rate/hour of each component you dont need to use that formula..you can directly use w=rt.

This is what you are asking rite??

Master | Next Rank: 500 Posts
Posts: 320
Joined: Sun Jan 13, 2008 10:00 pm
Thanked: 10 times

by ildude02 » Sun Jul 13, 2008 8:48 am
So you just add them up to get 9x and find x instead of using the formula?

Also, isn't there a formuale for even units along with time?

Units of A/TimeA + Unites B/TimeB = Total Units/TotalTime; when do we use this formulae? If we are given indivdual times and units produced by each of them and asked to find the missing units?

Appreciate your response.

Legendary Member
Posts: 829
Joined: Mon Jul 07, 2008 10:09 pm
Location: INDIA
Thanked: 84 times
Followed by:3 members

by sudhir3127 » Sun Jul 13, 2008 9:18 am
answer is E 1800..

A+A/2+3A= 2700

A=600
hence C= 1800