Let the total work to be done be X

now 6 machines take 12 days to complete X work

12=X/6 i.e X = 72

Therefore to complete work in 8 days we need 9 machines
8 = 72/ number of machines

addtional number of machines requires are 9-6 = 3

Master | Next Rank: 500 Posts
Posts: 132
Joined: Sun Apr 27, 2008 10:31 am
Location: Portugal
Thanked: 7 times

by atlantic » Sun Jun 22, 2008 10:06 am
Rosh,

If 6 machines do the job in 12 days, means that 1 machine alone will do the same job in 6*12=72 days.

If you divide the 72 days by 8 you get the number of machines that you need to perform the job = 9.