A compnay has two types of M/c, type R and type S. Operating at a constant rate, am/c of type R does a certain job in 36 hr and m/c type S does the sam job in 18 hr. If the copmany used the same # of each type to do this job in 2 hr, how many m/c of type R wer used?

3
4
6
9
12

We can easly cross out option a,b,d. I did it correct but some how I am not able to solve the problem.

Will appreciate any replies.

Thanks
VJ

OA=c
Source: — Problem Solving |

User avatar
GMAT Instructor
Posts: 1248
Joined: Thu Mar 29, 2012 2:57 pm
Location: Everywhere
Thanked: 503 times
Followed by:192 members
GMAT Score:780

by Bill@VeritasPrep » Tue May 08, 2012 8:09 am
Each type R has a rate of 1/36, and each type S has a rate of 1/18 (or 2/36). This means that each type S machine does twice as much work as each type R machine.

In order to complete the job in 2 hours, the combined rate of all machines must be 1/2 (or 18/36). Since each type S machine does twice as much work as each type R machine, then the total amount of work done by type S machines must be twice as much as the total amount of work done by type R machines.

Of the combined rate of 18/36, 12/36 must be type S and 6/36 must be type R.

Type S: 12/36 divided by the individual rate of 2/36 means that 6 type S machines were used.

Type R: 6/36 divided by the individual rate of 1/36 means that 6 type R machines were used.

Since the question asks about type R, the correct answer is C.
Join Veritas Prep's 2010 Instructor of the Year, Matt Douglas for GMATT Mondays

Visit the Veritas Prep Blog

Try the FREE Veritas Prep Practice Test

User avatar
Master | Next Rank: 500 Posts
Posts: 210
Joined: Thu Mar 08, 2012 11:24 pm
Thanked: 62 times
Followed by:3 members

by niketdoshi123 » Tue May 08, 2012 9:21 am

A compnay has two types of M/c, type R and type S. Operating at a constant rate, am/c of type R does a certain job in 36 hr and m/c type S does the sam job in 18 hr. If the copmany used the same # of each type to do this job in 2 hr, how many m/c of type R wer used?

3
4
6
9
12
# of machines used of each type = n
Rate of R = 1/36
Combined rate of all R machines= n/36
Rate of S = 1/18
Combined rate of all S machines= n/18

Combined Rate of all machines= 1/2
(n/36)+(n/18)=1/2
3*n/36=1/2
n=6
hence answer is C[/quote]

User avatar
GMAT Instructor
Posts: 15539
Joined: Tue May 25, 2010 12:04 pm
Location: New York, NY
Thanked: 13060 times
Followed by:1906 members
GMAT Score:790

by GMATGuruNY » Tue May 08, 2012 9:26 am
To avoid fractions, plug in a value for the job. I posted a solution here:

https://www.beatthegmat.com/gmat-prep-1- ... 08621.html
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3

User avatar
Senior | Next Rank: 100 Posts
Posts: 66
Joined: Mon Jun 07, 2010 3:12 am
Thanked: 10 times

by mdavidm_531 » Tue May 08, 2012 6:40 pm
Hi, Experts,

I see that this assumption is very important to the problem: "If the copmany used the same # of each type to do this job"

I wonder what will happen if such assumption is not stated. Would we need to have two equations?

Thanks