BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

work n Time

Expert replies
by sixpointer » Sat Oct 23, 2010 1:01 pm
17. A man starts a piece of work . Starting from the second day
onwards everyday new man joins .With every new man joining the
work that each man can do per day doubles .The work is completed in 5
days .On which day would they have completed the work ,if the work
that each of them could do per day had remained constant.?
1.10th 2.12th 3. 15th 4. 18th 5.16th
Join the discussion
Source: — Problem Solving |

by Stuart@KaplanGMAT » Sat Oct 23, 2010 8:28 pm
sixpointer wrote:17. A man starts a piece of work . Starting from the second day
onwards everyday new man joins .With every new man joining the
work that each man can do per day doubles .The work is completed in 5
days .On which day would they have completed the work ,if the work
that each of them could do per day had remained constant.?
1.10th 2.12th 3. 15th 4. 18th 5.16th
Let's say that on day 1, the man does x work.

On day 2, there are 2 men, each of whom do 2x work. So, 4x work gets done.

On day 3, there are 3 men, each of whom do 4x work. So, 12x work gets done.

On day 4, there are 4 men, each of whom do 8x work. So, 32x work gets done.

Finally, on day 5, there are 5 men, each of whom do 16x work. So, 80x work gets done.

Total: x + 4x + 12x + 32x + 80x = 129x work.

If the work remains constant, then the progression is:

x + 2x + 3x + 4x + 5x + .... + nx, on which n is the last day. We need that series to sum to 129.

Since we have a series of consecutive numbers, we could use the formula:

sum = # of terms * average of terms

but that's going to be some ugly math:

sum = n * (first term + last term)/2

129 = n * (1 + n)

129 = n + n^2

0 = n^2 + n - 129... some ugly quadratic!

So, rather than actually do all that ugly math, it's much quicker to backsolve at this point:

Starting with B or D, I'd choose D since it seems like we need a big number.

If n=18, then our sum is:

sum = 18 * (1+18)/2

sum = 18 * 9.5

sum = way too much!

Try B:

if n = 12, then we have:

sum = 12 * (1 + 12)/2

sum = 12 * 6.5

sum = way too small!

Accordingly, the answer has to be (C) 15.
Image

Stuart Kovinsky | Kaplan GMAT Faculty | Toronto

Kaplan Exclusive: The Official Test Day Experience | Ready to Take a Free Practice Test? | Kaplan/Beat the GMAT Member Discount
BTG100 for $100 off a full course
Join the discussion

by goyalsau » Sat Oct 23, 2010 8:51 pm
Dear Stuart

you did all the right thing but didn't notice that 15 will be = 120
and we need 129 and there is one option as 16.

So its 16 not 15

option E
Saurabh Goyal
[email protected]
-------------------------


EveryBody Wants to Win But Nobody wants to prepare for Win.
Join the discussion

by Stuart@KaplanGMAT » Sat Oct 23, 2010 9:26 pm
goyalsau wrote:Dear Stuart

you did all the right thing but didn't notice that 15 will be = 120
and we need 129 and there is one option as 16.

So its 16 not 15

option E
Ahh, my mistake was that I didn't look at choice E at all - on the GMAT, the choices are almost always in ascending or descending order, so I assumed (bad me!) that E was greater than D.

If I had noticed that E was lower than D, that would have affected the way that I backsolved the problem (I would have rearranged the answers so that I only had to check 2 of them).
Image

Stuart Kovinsky | Kaplan GMAT Faculty | Toronto

Kaplan Exclusive: The Official Test Day Experience | Ready to Take a Free Practice Test? | Kaplan/Beat the GMAT Member Discount
BTG100 for $100 off a full course
Join the discussion

by sixpointer » Sat Oct 23, 2010 10:58 pm
Stuart Kovinsky wrote:
sixpointer wrote:17. A man starts a piece of work . Starting from the second day
onwards everyday new man joins .With every new man joining the
work that each man can do per day doubles .The work is completed in 5
days .On which day would they have completed the work ,if the work
that each of them could do per day had remained constant.?
1.10th 2.12th 3. 15th 4. 18th 5.16th
Let's say that on day 1, the man does x work.

On day 2, there are 2 men, each of whom do 2x work. So, 4x work gets done.

On day 3, there are 3 men, each of whom do 4x work. So, 12x work gets done.

On day 4, there are 4 men, each of whom do 8x work. So, 32x work gets done.

Finally, on day 5, there are 5 men, each of whom do 16x work. So, 80x work gets done.

Total: x + 4x + 12x + 32x + 80x = 129x work.

If the work remains constant, then the progression is:

x + 2x + 3x + 4x + 5x + .... + nx, on which n is the last day. We need that series to sum to 129.

Since we have a series of consecutive numbers, we could use the formula:

sum = # of terms * average of terms

but that's going to be some ugly math:

sum = n * (first term + last term)/2

129 = n * (1 + n)

129 = n + n^2

0 = n^2 + n - 129... some ugly quadratic!

So, rather than actually do all that ugly math, it's much quicker to backsolve at this point:

Starting with B or D, I'd choose D since it seems like we need a big number.

If n=18, then our sum is:

sum = 18 * (1+18)/2

sum = 18 * 9.5

sum = way too much!

Try B:

if n = 12, then we have:

sum = 12 * (1 + 12)/2

sum = 12 * 6.5

sum = way too small!

Accordingly, the answer has to be (C) 15.

With every new man joining the work each Man can do per day double
Let each man can do one unit work

1st day ->1 unit

2nd day->2+1

3rd day ->4+2+1

4th day ->8+4+2+1

5th day ->16+8+4+2+1

Where Iam doing mistake ??:(

Please explain.

OA is 5th (16th)
Join the discussion

by pesfunk » Sun Oct 31, 2010 12:04 am
I think it should be:

1st day ->1 unit

2nd day->2+2

3rd day ->4+4+4

4th day ->8+8+8+8

5th day ->16+16+16+16+16

No of units completed = 1 + 4 + 12 + 32 + 80 = 129

No of days to complete the job in 2nd condition:
In 15 days no of units completed will be 15*16/2 = 120
In 16 days no of units completed will be 17*16/2 = 136

=> Work will be completed on 16th day