BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

How many more machines..

Expert replies
by adi_800 » Sat Sep 04, 2010 5:47 am
14) Six machines working at the same rate constant rate complete a job in 12 days. How many additional machines working at same rate will be needed to complete the job in 8 days?
a. 3
b. 6
c. 9
d. 12
e. 15


My approach : 12 days - 1 job - 6 machines
8 days - 1 job - how many machines

= 8 * 6 /12 = 4 machines...

So additional machines = 4 -1 = 3, which is indeed the OA...

Is my approach right?
Join the discussion
Source: — Problem Solving |

by shibal » Sat Sep 04, 2010 6:33 am
adi_800 wrote:14) Six machines working at the same rate constant rate complete a job in 12 days. How many additional machines working at same rate will be needed to complete the job in 8 days?
a. 3
b. 6
c. 9
d. 12
e. 15


My approach : 12 days - 1 job - 6 machines
8 days - 1 job - how many machines

= 8 * 6 /12 = 4 machines...

So additional machines = 4 -1 = 3, which is indeed the OA...

Is my approach right?
not really.....

you know that it takes 6 machines to complete the job in 12 days. so you can deduce that one machine makes 1/72 of the job in a day (6*12 = 72).

now, use the formula rate*time=work; from our previous analysis and from what is given in the statement, we know that work=72 and time=8. plug them in the formula to find the rate, which is equal to 9. thus you need 9 machines working at the rate given by the exercise to complete the job in 8 days. if you have 6 today, then 3 are necessary to complete the job. hope it helps.
Join the discussion

by selango » Sat Sep 04, 2010 8:19 am
Another easy approach..

6*12=x*8

x=6

Additional machines=3
--Anand--
Join the discussion

by selango » Sat Sep 04, 2010 8:22 am
adi_800 wrote:14) Six machines working at the same rate constant rate complete a job in 12 days. How many additional machines working at same rate will be needed to complete the job in 8 days?
a. 3
b. 6
c. 9
d. 12
e. 15


My approach : 12 days - 1 job - 6 machines
8 days - 1 job - how many machines

= 8 * 6 /12 = 4 machines...

So additional machines = 4 -1 = 3, which is indeed the OA...

Is my approach right?
the below formula can be used

M1*D1*H1/W1=M2*D2*H2/W2

M-Men or machines or persons

D-days

H-Number of hours

W=work
--Anand--
Join the discussion

by arora007 » Sat Sep 04, 2010 11:16 am
adi_800 wrote:14) Six machines working at the same rate constant rate complete a job in 12 days. How many additional machines working at same rate will be needed to complete the job in 8 days?
a. 3
b. 6
c. 9
d. 12
e. 15


My approach : 12 days - 1 job - 6 machines
8 days - 1 job - how many machines

= 8 * 6 /12 = 4 machines...

So additional machines = 4 -1 = 3, which is indeed the OA...

Is my approach right?
If 12 days are taken by 6 machines, it should logically stem that.. 8 days would only be possible when more than 6 machines are employed, how many more has to be figured out...


6 * 12 = 8 * (6+X)
Now X = 9 - 6 = 3
https://www.skiponemeal.org/
https://twitter.com/skiponemeal
Few things are impossible to diligence & skill.Great works are performed not by strength,but by perseverance

pm me if you find junk/spam/abusive language, Lets keep our community clean!!
Join the discussion

by GMATGuruNY » Sat Sep 04, 2010 11:19 am
Approach #1:

When the job is undefined, try plugging in your own number for the job.

Let's say each machine produces one unit each day. Then the 6 machines together would produce 6 units each day. Over 12 days, 6 * 12 = 72 units would be produced.

If we want to produce the 72 units in only 8 days, we'll need 72/8 = 9 units to be produced each day.

Since we'll need 3 more units to be produced each day, and each machine produces 1 unit per day, we'll need 3 more machines.

The correct answer is B.

Approach #2:

(number of machines) x (number of days) always has to yield the same amount of work.

So we could set up this equation:

(number of machines) x (number of days) = (number of machines) x (number of days)

6 * 12 = x * 8
72 = 8x
x = 9

Since we'll need 9 machines altogether, and we currently have 6, we'll need 9-6=3 more machines.

For all you math lovers: In math terms, the number of machines is inversely proportional to the number of days. When two values are inversely proportional, as one value goes up, the other must go down, so that their product is always the same. In the problem above, as the number of machines goes up, the number of days must go down, so that the product of the 2 values stays the same and we're always getting the same amount of work done.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Join the discussion

by Keeto702 » Sat Sep 04, 2010 1:21 pm
6 machines do the job in 12 days
thus 1 machine will do the job in 72 days (6*12)
Now we want the job to be done in 8 days so 72/8 = 9
which is 3 more than given 6 machines (9-6 = 3)


Let me know if my approach is crisp and simple