BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Knewton - Rate and work

Expert replies
by nikhilkatira » Wed Jul 14, 2010 9:03 pm
Eight workers from Company A can paint 7 homes in 84 hours. Working together, three workers from Company A and five workers from company B can paint 9 homes in 96 hours. If each worker from company A works at one constant rate, each worker from Company B works at another constant rate, and each home requires the same amount of work to paint, how many workers from Company B are required to paint 9 homes in 60 hours?

(A)12

(B)15

(C)18

(D)20

(E)30
Best,
Nikhil H. Katira
Join the discussion
Source: — Problem Solving |

by kvcpk » Wed Jul 14, 2010 11:56 pm
Let work perhour of a worker of A be a
Total manhours from A = 84*8a = 672a.
So 672a hours needed for 7 homes.

Let work per hour of B be b
(3a+5b)*96 hours are needed for 9 homes.
=288a+480b hours are needed for 9 homes.
Here, 288*7/672 homes can be built by 3a workers. = 3 homes.
Therefore 480b hours are needed for bulding 6 homes by B workers.
multiply by 1.5
720b hours are needed for bulding 9 homes.

Let the number of workers needed be X
Xb*60 hours are needed for 9 homes.
xb*60=720b
x=12

pick A.

What is OA?
Join the discussion

by ez2dj86 » Thu Jul 15, 2010 12:23 am
Let A be the work productivity for a worker in company A and B for that of company B.

8A can paint 7 homes in 84 hours.
8A=7/84
A=1/96 meaning one worker at company A can finish painting 1/96 of the house per hour.

3A+5B can paint 9 homes in 96 hours.
Substituting A=1/96 to this equation,
3(1/96)+5B=9/96
B=1/80 meaning one worker at company B can finish painting 1/80 of the house per hour.

So in 60 hours, one worker from company B can paint 60*(1/80)=3/4 of the house.

So to paint 9 homes, you need 9/(3/4)=12 workers