BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work work

Expert replies
by gmatmachoman » Thu Apr 29, 2010 4:12 am
50 persons can complete the work in 100 days. In how many days will the work be completed if 10 persons start the work and 10 person join after every 10 days?
Join the discussion
Source: — Problem Solving |

by liferocks » Thu Apr 29, 2010 4:24 am
Total amount of work is 50*100=5000 man-days

if x is the number of days to complete the work then

100+200+300+..till x terms =5000
or x/2{200+(x-1)100}=5000
or 100x+50x^2-50x=5000
or 50x^2+50x-5000=0
or x^2+x=100

for x=10, LHS becomes 10*11=110

hence the work will be complete on 100th day
Last edited by liferocks on Thu Apr 29, 2010 4:33 am, edited 2 times in total.
"If you don't know where you are going, any road will get you there."
Lewis Carroll
Join the discussion

by ajith » Thu Apr 29, 2010 4:29 am
gmatmachoman wrote:50 persons can complete the work in 100 days. In how many days will the work be completed if 10 persons start the work and 10 person join after every 10 days?
Total work = 5000 man days

Total work done in first 10 days = 100 man days
Total work done in second 10 days = 200 man days
Total work done in nth 10 days = n*100 mandays

sum = n(n+1)*50

now n(n+1)*50> 5000
n(n+1)> 100
n>10

till 10th 10 days work worth 4500 man days would be done

We have 110 people to finish remaining 500
who will finish it in 500/110 days
total days = 100 + 50/11
Always borrow money from a pessimist, he doesn't expect to be paid back.
Join the discussion

by liferocks » Thu Apr 29, 2010 4:34 am
ajith wrote:
gmatmachoman wrote:50 persons can complete the work in 100 days. In how many days will the work be completed if 10 persons start the work and 10 person join after every 10 days?
Total work = 5000 man days

Total work done in first 10 days = 100 man days
Total work done in second 10 days = 200 man days
Total work done in nth 10 days = n*100 mandays

sum = n(n+1)*50

now n(n+1)*50> 5000
n(n+1)> 100
n>10

till 10th 10 days work worth 4500 man days would be done

We have 110 people to finish remaining 500
who will finish it in 500/110 days
total days = 100 + 50/11
thanks .I made a mistake in calculation.edited it now.
"If you don't know where you are going, any road will get you there."
Lewis Carroll
Join the discussion

by harshavardhanc » Thu Apr 29, 2010 7:01 am
gmatmachoman wrote:50 persons can complete the work in 100 days. In how many days will the work be completed if 10 persons start the work and 10 person join after every 10 days?
in one day, 50 persons complete 1% of the work and a single person completes 1/50 % OR .02% of the work.

in 10 days 10 persons will complete 2% of the work.
in next ten days 20 persons will complete twice this i.e 4% of the work
in next 10, 30 persons will complete 6%

therefore, the total work done in intervals of 10 days becomes :

2+4+6+8+.....

sum of this Arithmetic progression till 9th term 90 = 90

on the 91st day, we have 100 persons working on the job, who complete 2% of the job/day. So, we need 5 more days to have the work completed.

IMO 95 days is the answer.

in ajith's solution, there are few points which are not clear to me :
ajith wrote:till 10th 10 days work worth 4500 man days would be done

We have 110 people to finish remaining 500
who will finish it in 500/110 days
total days = 100 + 50/11
"till 10th 10 days" means 90 days are over. So, while calculating the total days in the end it should be 90+ something.

moreover, on the 91st day we have 100 people not 110, the remaining fraction of work is 500/100.

Please correct me if I'm wrong.
Regards,
Harsha
Join the discussion

by sk818020 » Thu Apr 29, 2010 7:18 am
Is this the entire question?

The only reason I ask is because you couldn't really give an solid answer as the question is written. In the solutions above there is an assumption that all the workers are working at an equal and constant rate. The question does not tell us to make this assumption.

The reason this is an issue is what if 20% of the workers did 80% of the total work (some workers more efficient than others)? It would then be very relavent to know when those workers were added. More importantly you need to know the rate at which each individual worker worked to answer this questions with any certaintly, if the question does not state that all workers work at and equal and constant rate.

Thanks,

Jared
Join the discussion

by harshavardhanc » Thu Apr 29, 2010 7:32 am
sk818020 wrote:Is this the entire question?

The only reason I ask is because you couldn't really give an solid answer as the question is written. In the solutions above there is an assumption that all the workers are working at an equal and constant rate. The question does not tell us to make this assumption.

The reason this is an issue is what if 20% of the workers did 80% of the total work (some workers more efficient than others)? It would then be very relavent to know when those workers were added. More importantly you need to know the rate at which each individual worker worked to answer this questions with any certaintly, if the question does not state that all workers work at and equal and constant rate.

Thanks,

Jared
yes, you're correct. To solve this question, assumptions should be made. But, all these are assumptions,
are given as facts in the question itself which in normal cases. So, it doesn't hurt to assume general working efficiencies as same and start working on the numbers.

However, there is a BIG assumption that the workers can be more than 50. The first sentence says the work can be done by 50 workers in 100 days. So, someone might think that is the total number of persons who can work on the job. Answer in that case would be different.
Regards,
Harsha
Join the discussion

by sk818020 » Thu Apr 29, 2010 7:47 am
harshavardhanc wrote:
sk818020 wrote:Is this the entire question?

The only reason I ask is because you couldn't really give an solid answer as the question is written. In the solutions above there is an assumption that all the workers are working at an equal and constant rate. The question does not tell us to make this assumption.

The reason this is an issue is what if 20% of the workers did 80% of the total work (some workers more efficient than others)? It would then be very relavent to know when those workers were added. More importantly you need to know the rate at which each individual worker worked to answer this questions with any certaintly, if the question does not state that all workers work at and equal and constant rate.

Thanks,

Jared
yes, you're correct. To solve this question, assumptions should be made. But, all these are assumptions,
are given as facts in the question itself which in normal cases. So, it doesn't hurt to assume general working efficiencies as same and start working on the numbers.

However, there is a BIG assumption that the workers can be more than 50. The first sentence says the work can be done by 50 workers in 100 days. So, someone might think that is the total number of persons who can work on the job. Answer in that case would be different.
Well, generally speaking, all the questions are hypotheticals, but I've never seen a quant GMAT question where you had to make any further assumptions to get the answer. All the information you need should be in the question stem. I getting at that typically you won't see a question like this on the GMAT.

Thanks,

Jared