BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work and time

Expert replies
by eaakbari » Thu Apr 01, 2010 12:40 pm
A contract is to be completed in 46 days and 117 men were set to work,each working 8 hours a day. After 33 days, 4/7 of the work is completed.How many additional men may be employed so that the work may be completedin time, each man now working 9 hours a day?



From a prep review boook so no choices
Join the discussion
Source: — Problem Solving |

by eaakbari » Thu Apr 01, 2010 12:41 pm
4/7 of work is completed .
Remaining work=1- 4/7
=3/7
Remaining period= 46-33
=13 days
Less work, less men(direct proportion)
less days, more men(Indirect proportion)
More hours/day, less men(Indirect proportion)

work 4/7:3/7
Days 13:33 :: 117:x
hrs/day 9:8

(4/7)*13*9*x=(3/7)*33*8*117
x=(3*33*8*117) / (4*13*9)
x=198 men
So, additional men to be employed=198 -117=81
Join the discussion

by fibbonnaci » Fri Apr 02, 2010 10:54 am
hey i started this way: just want to know where i am making a mistake and how to proceed.

117 men take 46 days to complete the work in 8 hours.
so in 1 day 117 men will complete 1/46 of the work.
in 33 days -> 33/46 of the work is over
This equal the 4/7th of the work completed, where x= total work.

4x/7 = 33/46

so x= 33*7/4* 46

now 3/7th of the work is left pending. ie. 3/7 ( 33*7/4*46) => 99/4*46

Let y people be needed to worked for 9 hours for the rest 13 days (this y includes 117. so i will subtract 117 from y to get the answer)

99/4*46 = y* 9* 13

y= 99/4*46*9*13

now this will not even give an integer value. i know i am making a miss somewhr.
Join the discussion

by liferocks » Fri Apr 02, 2010 9:52 pm
fibbonnaci wrote:hey i started this way: just want to know where i am making a mistake and how to proceed.

117 men take 46 days to complete the work in 8 hours.
This is not stated in question.question says 117 men need to complete a piece of work in 46 days and they started to work for 8 days and finish 4/7 of work in 33 days.
so 117 men finish 4/7 of work in 33 x 8 man hours
rest of the calculation will follow from here.