-
vittalgmat
- Legendary Member
- Posts: 621
- Joined: Wed Apr 09, 2008 7:13 pm
- Thanked: 33 times
- Followed by:4 members
Nice one.
Machine A and Machine B are each used to manufacture 660 sprockets. It takes machine A 10 hours longer to produce 660 sprockets than machine B. Machine B produces 10 percent more sprockets per hour than machine A. How many sprockets per hour does machine A produce?
(A) 6
(B) 6.6
(C) 60
(D) 100
(E) 110
OA is A
Machine A and Machine B are each used to manufacture 660 sprockets. It takes machine A 10 hours longer to produce 660 sprockets than machine B. Machine B produces 10 percent more sprockets per hour than machine A. How many sprockets per hour does machine A produce?
(A) 6
(B) 6.6
(C) 60
(D) 100
(E) 110
OA is A












