BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Work problem

Expert replies
by oks » Fri Jun 12, 2009 4:50 pm
Crew A can build a complete car in 20 minutes and Crew B can build a complete car in 25 minutes. If both crews work independently and start at the same time, what is the shortest amount of time it oculd take for 10 cars to be complete?

A. 111 1/9 min
B. 115 2/5 min
C. 116 min
D. 120 min
E. 125 min

OA is D - could someone explain please? Maybe I am just missing the point. Thanks.
Join the discussion
Source: — Problem Solving |

Re: Work problem

by Naruto » Fri Jun 12, 2009 6:49 pm
oks wrote:Crew A can build a complete car in 20 minutes and Crew B can build a complete car in 25 minutes. If both crews work independently and start at the same time, what is the shortest amount of time it oculd take for 10 cars to be complete?

A. 111 1/9 min
B. 115 2/5 min
C. 116 min
D. 120 min
E. 125 min

OA is D - could someone explain please? Maybe I am just missing the point. Thanks.
A simple approach would be to take LCM of 20 and 25 mins which is 100 mins. Now in 100 mins each crew independently will complete 5 and 4 cars respectively, makin it a sum of 9. Now the question is to complete 10 cars in shortest possible time, 9 are done in 100 mins, the first crew will take less time to complete a car compared to the crew who takes 25 mins. so 10 cars can be done in 100+20 mins i.e 120 which is the answer. Hope this is clear.
Join the discussion

Re: Work problem

by ssmiles08 » Fri Jun 12, 2009 7:04 pm
Naruto wrote:
oks wrote:Crew A can build a complete car in 20 minutes and Crew B can build a complete car in 25 minutes. If both crews work independently and start at the same time, what is the shortest amount of time it oculd take for 10 cars to be complete?

A. 111 1/9 min
B. 115 2/5 min
C. 116 min
D. 120 min
E. 125 min

OA is D - could someone explain please? Maybe I am just missing the point. Thanks.
A simple approach would be to take LCM of 20 and 25 mins which is 100 mins. Now in 100 mins each crew independently will complete 5 and 4 cars respectively, makin it a sum of 9. Now the question is to complete 10 cars in shortest possible time, 9 are done in 100 mins, the first crew will take less time to complete a car compared to the crew who takes 25 mins. so 10 cars can be done in 100+20 mins i.e 120 which is the answer. Hope this is clear.
Good approach Naruto!
Join the discussion

by tohellandback » Fri Jun 12, 2009 7:50 pm
lets do it like this
crew A takes 20 minutes
crew B takes 25 minutes
if both had taken 20 minutes, 10 cars would have been ready in 100 minutes
but it is not the case. so lets say how far they go in 100 minutes
in 100 minutes
A makes 5 cars
B makes 4 cars
now 1 car is left
A takes 20 min, B takes 25. min is 20 min
so total time=100+20 =120 mins
The powers of two are bloody impolite!!