BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
GMATLiveTeach Starts Oct 17
Chris Peckover, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Chris Peckover, 100th-Percentile GMAT Scorer

Oct 17 · Chris Peckover
Sat · 11:00 AM to 2:00 PM ET
Oct 20 · Chris Peckover
Tue, Thu · 8:00 to 10:00 PM ET
Oct 25 · Josh Braslow
Sun · 1:00 to 4:00 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemand 5 seats left Start anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Rate problem

Expert replies
by notgoodinmath » Wed Jul 16, 2008 10:15 am
A pipe can fill a pool in 5 days. A 2nd pipe can fill the pool in 3 days. Assuming they start working together at the same time, how long will it take to fill the pool if the second pipe stops working after a day?

Please explain how the answer ends up being 10/3.

Thanks!!!!
Join the discussion
Source: — Problem Solving |

by ildude02 » Wed Jul 16, 2008 11:23 am
Since they both started working together, they both worked for 1 day. That means, 1/5th + 1/3rd of the pool is filled in 1 day(8/15th). For the rest of the pool(1-8/15), A alone has to fill it.

Since A filles 1/5th of the pool in 1 day, for 7/15th, it will take 7/3 days.

So the total time is 1 + 7/3 = 10/3 days. (we add 1 since both A and B worked for 1 day before B stopped working).

I would asusme there is a easier approach than this.
Join the discussion

Re: Rate problem

by kanha81 » Thu Apr 23, 2009 9:30 am
notgoodinmath wrote:A pipe can fill a pool in 5 days. A 2nd pipe can fill the pool in 3 days. Assuming they start working together at the same time, how long will it take to fill the pool if the second pipe stops working after a day?

Please explain how the answer ends up being 10/3.

Thanks!!!!
This is quite simple if you apply Logitech's method:

x/5 + 1/3 = 1 (b/c p2 worked only 1 day when they start work together)
=> x/5 = 2/3
=> x = 10/3
Want to Beat GMAT.
Always do what you're afraid to do. Whoooop GMAT
Join the discussion

Re: Rate problem

by doclkk » Thu Apr 23, 2009 10:13 am
notgoodinmath wrote:A pipe can fill a pool in 5 days. A 2nd pipe can fill the pool in 3 days. Assuming they start working together at the same time, how long will it take to fill the pool if the second pipe stops working after a day?

Please explain how the answer ends up being 10/3.

Thanks!!!!
since you're not good at math - (you said it, not me ...) - here's how you do it.

First pipe is 1/5 complete after a day and 2nd pipe is 1/3.

After one day they are 8/15 done and 2nd pipe stops working

Day 2 - 1/5 AKA 3/15 more gets finished (total is 11/15)

Day 3 - 1/5 AKA 3/15 more gets finished (total is 14/15)

Day 4 - only need 1/15 left to do, which is only 1/3 of a day or 1/15 of work.

That's pretty clear right?

Words like algebra and using algebra scare people like me so I like to explain things as basic as possible.