BREAKING: Target Test Prep releases Brand New 2026 On Demand GMAT prep course

Redeem

Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

★★★★★5.0559 reviews
Vote for Target Test Prep, Newsweek Readers’ Choice Awards 2026
NEWSWEEK READERS’ CHOICE 2026

BIG NEWS! Target Test Prep has been nominated, and they’d love your vote!

TTP has worked incredibly hard to build the best test prep experience possible, and winning Newsweek’s 2026 Readers’ Choice Award for Best Test Prep would mean a lot to them. If TTP has helped you, they’d be incredibly grateful for your vote. You can vote once each day through September 9.

Vote for TTP
GMATLiveTeach 7 seats left
Chris Peckover
NEXT LIVE COHORT

Oct 13 to Jan 7, 2027

with Chris Peckover

Schedule
Tue, Thu · 8:00 to 10:00 PM ET
Included
40 live hours + 6 months of GMAT OnDemand
  • Live instruction and real-time questions
  • Class recordings and assigned practice
View class & enroll
Limited cohort · enrollment openTarget Test Prep
EALiveTeach 5 seats left
Logan Thompson
EXECUTIVE ASSESSMENT

Sep 6 to Dec 6, 2026

with Logan Thompson

Schedule
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll
Limited cohort · enrollment openTarget Test Prep
GMATOnDemand Start anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

Compare the format, schedule, and included access before enrolling. Prices and seat counts shown reflect the supplied offer details.

Fruit Packers

Expert replies
by Aman verma » Fri Sep 17, 2010 10:25 am
Q: Green Dart is a renowned packager of fruits in L.A . It has 2 employees : a man and his wife .The man packs 70 mangoes or 56 guavas every day working 7 hours a day.His wife packs 30 mangoes or 24 guavas working 6 hours a day.The man has to pack 3300 mangoes and 2400 guavas with the help of his wife.They work alternatively , each day 10 hours.His wife started packaging on the first day and works on every alternate days.Similarly the man started his work on the second day and worked alternatively till the completion of the work. In how many days the work will be finished ?

a)84

b)85

c)86

d)87

e)88


OA[spoiler]a)[/spoiler]
800. Arjun's-Bird-Eye
Join the discussion
Source: — Problem Solving |

by Gmat Bond » Fri Sep 17, 2010 11:22 am
Are you sure it's a) ? I think it's c) .
The name is Bond, GMAT BOND !!
Join the discussion

by brijesh » Fri Sep 17, 2010 11:27 am
Aman verma wrote:Q: Green Dart is a renowned packager of fruits in L.A . It has 2 employees : a man and his wife .The man packs 70 mangoes or 56 guavas every day working 7 hours a day.His wife packs 30 mangoes or 24 guavas working 6 hours a day.The man has to pack 3300 mangoes and 2400 guavas with the help of his wife.They work alternatively , each day 10 hours.His wife started packaging on the first day and works on every alternate days.Similarly the man started his work on the second day and worked alternatively till the completion of the work. In how many days the work will be finished ?

a)84===Answer
Join the discussion

by Gmat Bond » Sat Sep 18, 2010 9:05 am
brijesh wrote:
Aman verma wrote:Q: Green Dart is a renowned packager of fruits in L.A . It has 2 employees : a man and his wife .The man packs 70 mangoes or 56 guavas every day working 7 hours a day.His wife packs 30 mangoes or 24 guavas working 6 hours a day.The man has to pack 3300 mangoes and 2400 guavas with the help of his wife.They work alternatively , each day 10 hours.His wife started packaging on the first day and works on every alternate days.Similarly the man started his work on the second day and worked alternatively till the completion of the work. In how many days the work will be finished ?

a)84===Answer
How ?
The name is Bond, GMAT BOND !!
Join the discussion

by diebeatsthegmat » Sat Sep 18, 2010 9:19 am
Gmat Bond wrote:
brijesh wrote:
Aman verma wrote:Q: Green Dart is a renowned packager of fruits in L.A . It has 2 employees : a man and his wife .The man packs 70 mangoes or 56 guavas every day working 7 hours a day.His wife packs 30 mangoes or 24 guavas working 6 hours a day.The man has to pack 3300 mangoes and 2400 guavas with the help of his wife.They work alternatively , each day 10 hours.His wife started packaging on the first day and works on every alternate days.Similarly the man started his work on the second day and worked alternatively till the completion of the work. In how many days the work will be finished ?

a)84===Answer
How ?
yeah the answer is A
Because they work alternative day, if the wife works the first day, the wife works the second day and then the husband the third day and wife fourth and so on
the first day his wife pack either mangoes or guavas but not both and so does the husband
so we calculate the number of days they packs mangoes first
the first day wife does 30 mangoes in 6 hours thus in 10 hours she packs 50 mangoes
the second day husband packs 70 in 7 hours thus in 10 hour he packs 100 mangoes
totally, in 2 days they packs 150 mangoes, so 3300 mangoes they pack in 44 days
we do the same with guavas and we get 40 days
so the final number is 40+44=84
hope it helps