A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?
(A) 4
(B) 5
(C) 6
(D) 7
(E) 8
[spoiler]Source: Picked from some source unknown to www.avenuesabroad.org[/spoiler]
(A) 4
(B) 5
(C) 6
(D) 7
(E) 8
[spoiler]Source: Picked from some source unknown to www.avenuesabroad.org[/spoiler]
The mind is everything. What you think you become. -Lord Buddha
Sanjeev K Saxena
Quantitative Instructor
The Princeton Review - Manya Abroad
Lucknow-226001
www.manyagroup.com
Sanjeev K Saxena
Quantitative Instructor
The Princeton Review - Manya Abroad
Lucknow-226001
www.manyagroup.com